603.9. Tolerances for Surface Regularity, Level, Thickness and Strength<br />

The tolerances for surface regularity, level, thickness and strength shall conform to the<br />

requirements given in Clause 903.5. Control of quality of materials and works shall be exercised<br />

by the Engineer in accordance with Section 900.<br />

603.10. Measurements for Payment<br />

The unit of measurement for concrete and rolled concrete pavement shall be the cubic meter of<br />

concrete placed, based on the net plan areas for the specified thickness shown on the drawings<br />

as directed by the Engineer.<br />

603.11. Rate<br />

The Contract unit rate payable for rolled cement concrete for base course shall be payment in full<br />

for carrying out the required operations including full compensation for all labour, materials and<br />

equipment, mixing, transport, placing, compacting, finishing, curing, testing and incidentals to<br />

complete the work as per <strong>Specification</strong>s, all royalties, fees, storage and rents where necessary<br />

and all leads and lifts.