The well shall be uniformly seated at the founding strata. It shall be ensured by lest borings that<br />

the properties of the soil encountered at the founding strata and upto a depth of one and a half times<br />

the well diameter is identical to that adopted in the design. The procedure<br />

for test borings shall satisfy the provisions of these specifications. In case the soil encountered is<br />

inferior to that adopted in design, the well shall be re-designed by the Engineer adopting the soil<br />

properties actually encountered and the founding level intimated to the Contractor, who shall carry out<br />

the work.<br />

In case of seating of wells in hard rocky strata, where the rock profile is steeply sloping,<br />

pneumatic methods of sinking may be adopted to seat the well evenly as directed by the Engineer. The<br />

decision of adopting pneumatic sinking shall be taken by the Engineer. The cutting edge may also be<br />

embedded for a suitable depth in the rocky strata, as decided by the Engineer keeping in view the<br />

quality of rock. As an additional measure of safety, the well shall be anchored to the rocky strata by<br />

anchor bars provided in the steining of the well, as shown on the drawing irrespective of the fact that<br />

tension develops or not at the base of the well under design loads. After the well has been evenly<br />

seated on good hard rock, arrangements shall be made to facilitate proper inspection in dry and visible<br />

conditions before the bottom plug is laid.<br />

1208. BOTTOM PLUG<br />

For bottom plug, the concrete mix shall be designed (in dry condition) to attain the concrete<br />

strength as mentioned on the drawing and shall contain 10 per cent more cement than that required for<br />

the same mix placed dry, to cater for underwater concreting. However, the total cement content shall<br />

not be less than 363 kg/cu.m. of concrete with a slump in the range of 150 mm to 200 mm. Admixtures<br />

may be added to the concrete to impart the required characteristics indicated herein.<br />

Concrete for the bottom plug shall be laid by tremie pipe method. Tremie concrete when started<br />

shall be continued without interruption for full concreting in the bottom plug. The concrete production<br />

equipment and placement equipment should be sufficient to enable under water concreting within<br />

stipulated time. Necessary standby equipment should be available for emergency situation.<br />

Before commencing plugging, all loose material from the bottom of the well shall be removed.<br />

Concreting shall be done in one continuous operation till the dredge hole is filled upto the<br />

required height and thereafter sounding shall be taken upto ensure that the concrete has been laid to<br />

he required height.<br />

Least disturbance shall be caused to the water inside the welt while laying concrete in the<br />

bottom plug.<br />

Concrete shall not be disturbed in any way for at least 14 days.<br />

In order to check any rise in the lev el of the bottom plug soundings should be taken at the<br />

close of concreting and once every day for the subsequent 3 days.<br />

The soundness of the bottom plug may be tested by dewatering the well by 5 metres below the<br />

surrounding water level and checking the rise of water. The rate of rise shall preferably be less than 10<br />

cms per hour. In case the rate is higher, suitable remedial measures as directed by the Engineer, shall<br />

be taken by the Contractor at his own cost.<br />

1209. SAND FILLING<br />

Sand filling shall commence after a period of 3 days of laying of bottom plug. Also, the height of<br />

the bottom plug shall be verified before starling sand filling.<br />

Sand shall be clean and free from earth, clay clods, roots, boulders, shingles, etc. and shall be<br />

compacted as directed. Sand filling shall be carried out upto the level shown on the drawing, or as<br />

directed by the Engineer,<br />

1210. TOP PLUG<br />

After filling sand upto the required level a plug of concrete shall be provided over it as shown on<br />

the drawing, or as directed by the Engineer.