minimum dry density as given in Table 300-3.<br />

In case where the difference between the sub-grade level (top of the sub-grade on which pavement<br />

rests) and ground level is less than 0.5 m and the ground does not have 98 percent relative compaction<br />

with respect to the dry density (as given in Table 300-3), the ground shall be loosened upto a level 0.5<br />

m below the sub-grade level, watered and compacted in layers in accordance with Clauses 305.3.5 and<br />

305.3.6 to achieve dry density not less than 98 percent relative compaction as given in Table 300-3.<br />

Where so directed by the Engineer, any unsuitable material occurring in the embankment foundation<br />

(500 mm portion just below the sub-grade) shall be removed, suitably disposed and replaced by<br />

approved materials laid in layers to the required degree of compaction.<br />

305.3.5 Spreading material in layers and bringing to appropriate moisture content<br />

305.3.5.1 In construction of embankment/ sub-grade the construction material shall be spread in layers<br />

of uniform thickness not exceeding 200 mm compacted thickness over the entire width of embankment<br />

by mechanical means, finished by a motor grader. It shall be compacted as per Clause 305.3.6.<br />

Successive layers shall not be placed until the layer under construction has been thoroughly compacted<br />

to the specified requirements as in Table 300-3 and got approved by the Engineer-in-charge. Each<br />

compacted layer shall be finished parallel to the final cross-section of the embankment.<br />

305.3.5.2 Prior to commencement of compaction the Moisture content of the material shall be checked<br />

at the site of placement as per IS 2720 <strong>Part</strong>-2 if found to be out of specified limits, the same shall be<br />

made good. Where water is required to be added in such constructions, water shall be sprinkled by a<br />

water tanker fitted with sprinkler. The water shall be added uniformly and thoroughly mixed in soil by<br />

blading, harrowing until a uniform moisture content is obtained throughout the depth of the layer.<br />

If the moisture content found more than specified limit than it shall be dried by aeration and exposure to<br />

the sun, till the moisture content is acceptable for compaction. Compaction work shall be suspended till<br />

the moisture is accepted for compaction.<br />

Moisture content of each layer of soil shall be checked in accordance with IS: 2720 (<strong>Part</strong> 2), and unless<br />

otherwise mentioned, shall be so adjusted, making due allowance for evaporation losses, that at the<br />

time of compaction it is in the range of 1 percent above to 2 percent below the optimum moisture<br />

content determined in accordance with IS: 2720 (<strong>Part</strong> 8) as the case may be. Expansive clays shall,<br />

however, be compacted at moisture content corresponding to the specified dry density, but on the wet<br />

side of the optimum moisture content obtained from the laboratory compaction curve.<br />

Clods or hard lumps of earth shall be broken to have a maximum size of 75 mm when being placed in the<br />

embankment and a maximum size of 50 mm when being placed in the sub-grade.<br />

305.3.6 Compaction: The compaction equipment of suitable size & capacity as approved by the<br />

Engineer-in-charge shall be employed to compaction work. The compaction equipment are static three<br />

wheel roller, self propelled single drum vibratory roller, vibratory tandem roller, pneumatic tyred, pad foot<br />

rollers, etc. The compaction equipments may be used either individually or in suitable combinations.<br />

The Contractor shall demonstrate the efficacy of the equipment he intends to use by carrying out<br />

compaction trials. The procedure to be adopted for these site trials shall first be submitted to the<br />

Engineer-in-charge for approval.<br />

Each layer of the material shall be thoroughly compacted to the densities specified in Table 300-3.<br />

Subsequent layers shall be placed only after the finished layer has been tested according to Clause<br />

903.2.2 and accepted by the Engineer-in-charge.<br />

If density measurements shows reveal any soft areas in the embankment /sub-grade/earthen shoulders<br />

than, further compaction shall be carried out as directed by the Engineer. If inspite of that the specified<br />

compaction is not achieved, the material in the soft areas shall be removed and replaced by approved<br />

material & than compacted using appropriate compactor such as light weight vibratory roller, double<br />

drum walk behind roller, vibratory plate compactor, trench compactor or vibratory tamper to the density<br />

requirements and satisfaction of the Engineer-in-charge.<br />

305.3.7 Drainage: The surface of the embankment/sub-grade at all times during construction shall be