27.01.2015 Views

Specification Part 3 - Road & Bridge Works - Urban Administration ...

Specification Part 3 - Road & Bridge Works - Urban Administration ...

Specification Part 3 - Road & Bridge Works - Urban Administration ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

602.8.2. At all times sufficient forms shall be used and set to the required alignment for at least<br />

200 m length of pavement immediately in advance of the paving operations, or the anticipated<br />

length of pavement to be laid within the next 24 hrs whichever is more,<br />

602.8.3. Use of guide wires<br />

602.8.3.1. Where slip form paving is proposed, a guide wire shall be provided along both sides of<br />

the slab, Each guide wire shall be at a constant height above and parallel to the required edges of<br />

the slab as described in the contract/drawing within a vertical tolerance of ± 3mrn. Additionally,<br />

one of the wires shall be kept al a constant horizontal distance from the required edge of the<br />

pavement as indicated in the contract/drawing within a lateral tolerance of ± 10 mm.<br />

602.8.3.2. The guide wires shall be supported on stakes not more than 8 mm apart by connectors<br />

capable of fine horizontal and vertical adjustment. The guide wire shall be lensioned on the<br />

stakes so that a 500 gram weight shall produce a deflection of not more than 20 mm when<br />

suspended at the mid point between any pair of stakes. The ends of the guide wires shall be<br />

anchored to fixing point or winch and not on the stakes.<br />

602.8.3.3. The stakes shall be positioned and the connectors maintained at their correct height<br />

and alignment from 12 hours on the day before concreting takes place until 12 hours after<br />

finishing of the concrete. The guide wire shall be erected and tensioned on the connectors at any<br />

section for al least 2 hours before concreting that section.<br />

602.8.3.4. The Contractor shall submit to the Engineer for his approval of line and level, the<br />

stakes and connectors which are ready for use in the length of road to be constructed by 12<br />

hours on the working day before the day of construction of slab. Any deficiencies noted by the<br />

Engineer shall be rectified by the Contractor who shall then re-apply for approval of the affected<br />

stakes. Work shall not proceed until the Engineer has given his approval. It shall be ensured that<br />

the stakes and guide wires are not affected by the construction equipment when concreting is in<br />

progress.<br />

602.9. Construction<br />

602.9.1. General: A systems approach may be adopted for construction of the pavement, and the<br />

Method Statement for carrying out the work, detailing all the activities including indication of timecycle,<br />

equipment, personnel etc., shall be got approved from the Engineer before the<br />

commencement of the work, The above shall include the type, capacity and make of the batching<br />

and mixing plant besides the hauling arrangement and paving equipment. The capacity of paving<br />

equipment, batching plant as well as all the ancillary equipment shall be adequate for a paving<br />

rate of at least 300 m in one day.<br />

602.9.2. Batching and mixing: Batching and mixing of the concrete shall be done at a central<br />

batching and mixing plant with automatic controls, located at a suitable place which takes into<br />

account sufficient space for stockpiling of cement, aggregates and stationary water tanks. This<br />

shall be, however, situated at an approved distance, duly considering the properties of the mix<br />

and the transporting arrangements available with the Contractor.<br />

602.9.3. Equipment for proportioning of materials and paving<br />

602.9.3.1. Proportioning of materials shall be done in the batching plant by weight, each type of<br />

material being weighed separately. The cement from the bulk stock may be weighed separately<br />

from the aggregates and water shall be measured by volume. Wherever properly graded<br />

aggregate of uniform quality cannot be maintained as envisaged in the mix design, the grading of<br />

aggregates shall be controlled by appropriate blending techniques. The capacity of batching and<br />

mixing plant shall be at least 25 per cent higher than the proposed capacity of the laying/paving<br />

equipment.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!