The earth work in construction of embankment for guide bund shall be measured in cubic<br />

metres unless otherwise specified.<br />

The boulders/cement concrete blocks and wire crates in apron shall be measured in cubic<br />

metres.<br />

The filter and stone pitching shall be measured separately in cubic metres unless otherwise<br />

specified.<br />

Rubble stone/cement concrete blocks, flooring and cement concrete<br />

measured in cubic metres for each class of material.<br />

bedding shall be<br />

Preparation of base for laying the flooring shall be deemed incidental to the work.<br />

For laying apron, excavation upto an average depth of 150 mm shall be deemed to be included<br />

in the main item and shall not be measured separately unless otherwise specified. Excavation more<br />

than 150 mm shall be measured in cubic metres as given in Clause 304.<br />

2510. RATE<br />

The contract unit rate for the construction of embankment for guide bund shall cover the cost of<br />

all materials including transportation, laying, compacting, all labour, tools, equipment, sampling and<br />

testing, supervision and all incidentals necessary for completing the work according to these<br />

specifications.<br />

The contract unit rate for one cubic metre of finished work of apron shall include the cost of all<br />

material, labour, tools and plant for completing the work according to above specifications. Excavation<br />

upto an average depth of 150 mm shall also be deemed to be included in the rate as dressing of the<br />

bed. Excavation beyond this depth shall be paid for separately unless otherwise specified. The contract<br />

unit rate for one cubic metre of filter or stone/cement concrete block pitching on slopes shall include the<br />

cost of preparing the bases, putting to the profiles, laying and compacting the filter and stone pitching of<br />

dry rubble/cement concrete block rivetment for embankment slopes to the specified thickness, lines,<br />

curves, slopes and levels and all labour and materials as well as tools and plant required for the work.<br />

The contract unit rate for rubble stone/cement concrete block flooring shall include the cost of all<br />

material, labour and tools and plant for completing the work as per these specifications.