joints is completed including the construction of shoulder, with the written permission of the<br />

Engineer.<br />

602.14. Tolerances for Surface Regularity, Level, Thickness and Strength<br />

The tolerances for surface regularity, level, thickness and strength shall conform to the<br />

requirements given in Clause 903.5. Control of quality of materials and works shall be exercised<br />

by the Engineer in accordance with Section 900.<br />

602.15. Measurements for Payment<br />

602.15.1. Cement Concrete pavement shall be measured as a finished work in square meters<br />

with specified thickness. The volume to be paid for will be calculated on the basis of thickness<br />

and plans shown on the project drawings and adjusted for the deficiency in thickness. No<br />

additional payment shall be made for extra thickness of the slab. The full payment will be made to<br />

this item after 28 days strength of the concrete is found to be satisfactory.<br />

The unit for measurement for concrete pavement shall be the cubic meter of concrete placed,<br />

based on the net plan areas for the specified thickness shown on the Drawings or directed by the<br />

Engineer. The rate shall include all provisions of this <strong>Specification</strong> and shall include the provision<br />

of all materials including polythene film, concrete, stock piling, mixing, transport, placing,<br />

compacting, finishing, curing together with all formwork, and including testing and submission of<br />

test certificates and records. No deduction shall be made in measurement for openings provided<br />

that the area of each is less than 0.5 sq. m. The unit rate as entered in the Bill of Quantities shall<br />

also include the full costs of contraction, expansion, construction, and longitudinal joints. It shall<br />

also include joint filler, keys, caulking rod, debonding strip, sealant primer, joint sealant, dowel bar<br />

and tie rod.<br />

602.15.2. Pavement thickness<br />

All precautions and care shall be taken to construct pavement having uniform thickness as called<br />

for on the plans.<br />

Thickness of the cement concrete pavement shall be calculated on the basis of level<br />

data of the cement concrete-pavement and the underlying sub-base taken on a grid of 5 m x 3, 5<br />

m or 6, 25 rri x 3.5 m, the former measurement being in longitudinal direction.<br />

A day’s work is considered as a ’lot’ for calculating the average thickness of the slab. In<br />

calculating the average thickness, individual measurements which are in excess of the specified<br />

.thickness by more than 10 mm shall be considered as the specified thickness plus 10 mm.<br />

Individual areas deficient by more than 25 mm shall be verified by the Engineer by<br />

ordering core cutting and it in his opinion the deficient areas warrant removal, they shall be<br />

removed and replaced with concrete of the thickness shown on the plans.<br />

When the average thickness for the lot is deficient by the extent shown in Table 600-3,<br />

the Contract unit price will be adjusted as per this Table.<br />

TABLE 600-3. PAYMENT ADJUSTMENT FOR DEFICIENCY IN THICKNESS<br />

Deficiency in the average<br />

thickness of day’s work<br />

Per cent of Contract<br />

unit price payable<br />

Up to 5 ram<br />

6 - 10 mm<br />

11 - 15 mm<br />

16 - 20 mm<br />

21 - 25 mm<br />

100<br />

87<br />

SI<br />

75<br />

70<br />

In the stretch where deficiency of average thickness is more than 25 mm, the section whose<br />

thickness is deficient by 26 mm or more is identified with the help of cores. Such slabs shall be<br />

removed and reconstructed at the cost of the Contractor, During such rectification work, care<br />

shall be taken to replace full slab and to the full depth.