(4) Rolling shall be discontinued when the aggregates are partially compacted with sufficient void space in them<br />

to permit application of screenings.<br />

(5) However, where screenings are not to be applied, as in the case of crushed aggregates like brick metal,<br />

laterite and kankar, compaction shall be continued until the aggregates are thoroughly keyed.<br />

(6) Curing rolling, slight sprinkling of water may be done, if necessary.<br />

(7) Rolling shall not be done when the sub grade is soft or yielding or when it causes a wave- like motion in the<br />

sub grade or sub base course.<br />

(8) The rolled surface shall be checked transversely and longitudinally, with templates and any irregularities<br />

corrected by loosening the surface, adding or removing necessary amount of aggregates and re -rolling until the<br />

entire surface conforms to desired cross fail (camber) and grade. In no case shall the use of screenings be<br />

permitted to make up depressions.<br />

(9) Material which gets crushed excessively during compaction or becomes segregated shall be removed and<br />

replaced with suitable aggregates.<br />

(10) It shall be ensured that shoulders are built up simultaneously along with water bound macadam courses as<br />

per Clause 407.4.1.<br />

404.3.5. Application of screenings: (1) After the coarse aggregate has been rolled to Clause 404.3.4,<br />

screenings to completely fill the interstices shall be applied gradually over the surface. These shall not be damp<br />

or wet at the time of application.<br />

(2) Dry rolling shall be done while the screenings are being spread so that vibrations of the roller ca use them to<br />

settle into the voids of the coarse aggregate.<br />

(3) The screenings shall spread uniformly in successive thin layers either by the spreading .motions of hand<br />

shovels or by mechanical spreaders, or by any other machine so that the course aggregate shall not be<br />

disturbed.<br />

(4) The screenings shall be applied at a slow and uniform rate (in three or more applications) so as to ensure<br />

filling of all voids. This shall be accompanied by dry rolling and brooming with mechanical brooms, hand brooms<br />

or both.<br />

(5) In no case shall the screenings be applied as fast and thick as to form cakes or ridges on the surface in such<br />

a manner as would prevent filling of voids or prevent the direct bearing of the roller on the coarse aggregate.<br />

(6) These operations shall continue until no more screenings can be forced into the voids of the coarse<br />

aggregate.<br />

(7) The spreading, rolling, and brooming of screenings shall be carried out in only such lengths of the road<br />

which could be completed within one day’s operation.<br />

404.3.6. Sprinkling and grouting: After the screenings and rolling the surface shall be copiously sprinkled with<br />

water, swept and rolled.<br />

(2) Hand brooms shall be used to sweep the wet screenings into voids and to distribute them evenly.<br />

(3) The sprinkling, sweeping and rolling operation shall be continued, and additional screenings apply where<br />

necessary until the coarse aggregates are well bonded and firmly set for the entire depth and until a grout has<br />

been formed of screenings and water that will fill all void and formed a wave of grout a head of the wheel to the<br />

roller.