12.07.2015 Views

2009 Scenario Reliability Assessment - NERC

2009 Scenario Reliability Assessment - NERC

2009 Scenario Reliability Assessment - NERC

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Scenario</strong> <strong>Reliability</strong> Self-<strong>Assessment</strong>scenters are situated. The distance between these large generation complexes and the load centersare in the order of 700 to 800 miles.TransÉnergie, the Transmission Operator, operates an extensive transmission system in order toprovide the necessary access to resources and to loads. The following table shows the mainload-end substations and associated transmission to be built during the study horizon.Table Québec-5: Projected Transmission AdditionsVoltage Length In-ServiceTransmission Project Name (KV) (Miles) Date(s)From / ToIn Progress - New InstallationsMont-Tremblant station 120-25 kV Dec-<strong>2009</strong>and Line 120 4,8 Dec-<strong>2009</strong>Vaudreuil-Soulanges station 120-25 kV Nov-<strong>2009</strong>In Progress - RestorationsDelson station 120 Nov-<strong>2009</strong>Saint-Basile station 120 Nov-2010Sorel Station 120 Nov-2010Planned - New InstallationsAnne- Hébert station 315-25 kV Fall 2010and Line 315 8,2 Fall 2010Beauceville - Sainte-Marie 120 18,6 Spring 2011Montcalm station 230-25 kV 2012Neubois station 120-25 kV Fall 2012No delay with any of these projects is expected. A delay in any particular project would notaffect Bulk System reliability.Operational IssuesThere are no significant anticipated unit outages, variable resources, transmission outages ortemporary operating measures that are anticipated to impact reliability during the next ten years.One major anticipated unit outage (Gentilly-2 nuclear unit of 675 MW) is scheduled from late2010 to mid-2012 but this outage will not impact reliability. Variable resources, transmissionadditions and temporary operating measures are not expected to negatively impact reliabilityduring the next ten years.Non-hydraulic resources account only for a small portion of total resources. Plants using oil orjet fuel are refuelled by boat or by truck and generally not during the winter season. Natural gasis used at a single cogeneration plant and is delivered under a firm natural gas purchase contract.Operational planning studies are being continuously conducted by TransÉnergie, the QuébecArea controller. Yearly peak demand period studies are conducted to assess system conditionsduring winter peak periods. Extreme weather in Québec translates into very low temperaturesduring the Winter Operating Period. Through a transmission planning criterion, transmissionplanning studies must take into account a 4,000 MW load increase above the normal load<strong>2009</strong> <strong>Scenario</strong> <strong>Reliability</strong> <strong>Assessment</strong> Page 115

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!