12.07.2015 Views

2009 Scenario Reliability Assessment - NERC

2009 Scenario Reliability Assessment - NERC

2009 Scenario Reliability Assessment - NERC

SHOW MORE
SHOW LESS
  • No tags were found...

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>Scenario</strong> <strong>Reliability</strong> Self-<strong>Assessment</strong>s<strong>Scenario</strong> <strong>Assessment</strong> for the MRO-Canada SubregionManitobaManitoba Hydro’s currently planned renewable capacity additions include 300 MW of windcapacity and 90 MW of hydro capacity. The wind generation is currently planned to be added inincrements of 100 MW in 2011/12, 2012/13, and 2013/14. To serve future load obligations, anadditional 90 MW of new hydro generation is also planned for a 2017/18 in-service date. This90 MW installation would be the first unit of a new 695 MW hydro plant expected to becompleted by 2020.Resource adequacy is expected to improve as the hydro resource listed above is installed.However, the additional wind power would not be able to contribute capacity to meet Manitoba’swinter peak, as the wind turbines would be shut down due to low temperature (colder than -20°Fat times the winter peak occurs). The 90 MW of hydro would be dispatchable and would serve asa 90 MW capacity resource. The amount of external resource that Manitoba would have to relyon to meet planning reserve margins is not expected to change as these new resources becomeavailable.From a transmission adequacy standpoint, sufficient new transmission is planned to be built toensure deliverability of the added resources. Manitoba Hydro’s study methodology for aNetwork Resource assumes full nameplate generation is available at peak load for determiningthe necessary transmission infrastructure.The wind resources within Manitoba are located fairly close to major load centers or major 230kV stations and transmission lines. An exploratory study was first performed that analyzed thetransmission requirements for alternative locations of 300 MW of new wind in Manitoba. Thestudy concluded there are numerous locations where wind can be economically and reliablyinterconnected.The preferred location for the 300 MW wind project is the Letellier 230 kV station, which isabout 60 miles south of Winnipeg. Manitoba Hydro is planning to construction a third 2,000MW HVdc bipole line by 2017 to enhance the reliability of HVdc transmission system from itsnorthern generation to load centers in southern Manitoba. The hydro generation identified abovewould be delivered to load over this new HVdc bipole line.The reactive power requirements for a hydro plant are similar to a wind plant. The hydro plantmust provide a minimum of 0.9 leading and lagging power-factor capability as measured at themachine terminals. The hydro plants must also provide automatic voltage control and a highinitial response excitation system with a power system stabilizer because of the unit size. Thewind plant must provide 0.95 leading and lagging power at the point of interconnection atnominal voltage and full output. Some deviations are permissible based on the terminal voltage.The wind plant must also provide voltage regulation. A full range of disturbances are applied todetermine if the reactive power capability is adequate to meet <strong>NERC</strong> and MRO planningstandards.Page 52<strong>2009</strong> <strong>Scenario</strong> <strong>Reliability</strong> <strong>Assessment</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!