THE COAL TRADE BULLETIN. 23<br />
STATUS OF OHIO RIVER IMPROVEMENTS AS SHOWN BY UNITED<br />
STATES ENGINEER'S REPORT<br />
Inquiry having been made regarding the status<br />
of the improvements in the Ohio river, THE COAL<br />
TRADE BULLETIN prints below the official data<br />
on this work as taken from the records of Col.<br />
Francis Shunk, U. E. Engineer, Pittsburgh, December<br />
1, 1913.<br />
The list shows official number of dam, distance<br />
below Pittsburgh, nearest railroad station or town<br />
to site, and status of work:<br />
No. 1—4.7 miles. Bellevue, Pa., Davis Island<br />
dam, completed and in operation.<br />
No. 2—9 miles, Glenfield, Pa„<br />
dam, completed and in operation.<br />
No. 3—10.9 miles, Glen Osborne,<br />
and in operation.<br />
No. 4—18.6 miles Legionville,<br />
and in operation.<br />
No. 5—23.9 miles. Freedom, Pa.<br />
in operation.<br />
Neville Island<br />
Pa., completed<br />
Pa completed<br />
completed and<br />
No. 6—28.8 miles, Merrill, Pa., Beaver dam. completed<br />
and in operation.<br />
No. 7—36.9 miles. Midland, Pa., under construction<br />
by contract, about 85 per cent, completed.<br />
No. 8—46.1 miles, Wellsville, 0., completed and<br />
in operation.<br />
No. 9—55.6 miles, New Cumberland, W. Va., under<br />
construction by contract, about 92 per cent.<br />
completed.<br />
No. 10—65.7 miles, Steubenville, 0., under construction<br />
by contract, about 41 per cent, completed.<br />
No. 11—76.3 miles, Wellsburg, W. Va., completed<br />
and in operation.<br />
No. 12—87 miles, Wheeling, W. Va.. under construction<br />
by contract, about 49 per cent, completed.<br />
No. 13—95.8 miles, McMechen, XV. Va., completed<br />
and in operation.<br />
No. 14—113.8 miles, Woodland, W. Va., under construction<br />
by contract, about 34 per cent, completed.<br />
No. 15—128.9 miles, two miles below- New Martinsville,<br />
W. Va., under construction by contract,<br />
about 58 per cent, completed.<br />
No. 16—146.4 miles, S l 2 miles below Sistersville,<br />
W. Va., near New Matamoras. 0., under construction<br />
by contract made in 1913, probably completed<br />
and in operation in 1918.<br />
No. 17—167.4 miles, two miles below Waverly,<br />
W. Va., under construction by contract made in<br />
1913, probably completed and in operation in 1918.<br />
No. 18—179.3 miles, Constitution, 0., Marietta<br />
harbor, eight miles below- Marietta, 0., completed<br />
and in operation.<br />
No. 19—191.4 miles, Little Hocking, 0., Parkersburg<br />
harbor, eight miles below Parkersburg, W.<br />
Va., tinder construction by contract, about 62 per<br />
cent, completed.<br />
No. 20—201.7 miles, Belleville, W. Va., under<br />
construction by contract, about 50 per cent, completed.<br />
No. 21—213.S miles, Buffington Island, five tniles<br />
above Ravenswood, W r . Va., land purchased and<br />
plans prepared, funds for construction not available.<br />
No. 22—220.1 miles, two miles below Ravenswood,<br />
XV. Va., land purchased and plans prepared,<br />
funds for construction not available.<br />
No. 23—230.6 miles, 1 (L. miles above Millwood,<br />
W. Va., land purchased and plans prepared, funds<br />
for construction not available.<br />
No. 24—242 miles, one mile below Racine, O.,<br />
under construction by contract made in 1913, probably<br />
completed and in operation in 1918.<br />
No. 25—260 miles, four miles below Point Pleasant,<br />
XV. Va.. land purchased and plans prepared,<br />
funds for construction not available.<br />
No. 26—278 miles, Hogsett, W. Va., now rebuilding<br />
by hired labor, probably completed and in operation<br />
in 1915.<br />
No. 27—300.3 miles. Crown City, O., land purchased<br />
and plans prepared, funds for construction<br />
not available.<br />
No. 28—309 miles, two miles below Huntington,<br />
XV. Va., under construction by hired labor, probably<br />
completed and in operation in 1915.<br />
No. 29—319.4 miles, two miles below Ashland,<br />
Ky., under construction by contract, about 53 per<br />
cent, completed.<br />
No. 30—338.9 miles, six miles below Greenup,<br />
Ky., purchase of land in progress, funds for construction<br />
not available<br />
No. 31—358.4 miles, five miles below Portsmouth,<br />
O., under construction by contract, about 9 per<br />
cent, completed.<br />
No. 32—3S3.7 miles, three miles below Concord,<br />
Ky., purchase of land in progress, funds for construction<br />
not available.<br />
No. 33—404 miles, four miles above Maysville,<br />
Ky., purchase of land in progress, funds for construction<br />
not available.<br />
No. 34—432.8 miles, Chilo, O., purchase of land in<br />
progress, funds for construction not available.<br />
No. 35—449.7 miles, four miles below Richmond,<br />
O., under construction by contract made in 1913.<br />
probably completed and in operation in 1918.<br />
No. 36—459.5 miles, California, O.. six miles<br />
above Cincinnati, O., land not yet purchased, funds<br />
for construction not available.<br />
No. 37—481.3 miles, Saylers Park, O., 12 miles<br />
.1