24<br />
Mounting and alignment of the vertical sections:<br />
11<br />
Drain-off<br />
sheet left<br />
50mm<br />
Drain-off sheet with system-specific<br />
width (marked with a ”V”)<br />
V<br />
Use the brackets for the upper flow sheets as<br />
spacers (the bracket with system-specific width is<br />
marked with a “V”)<br />
V<br />
Drain-off sheet right<br />
11. Use the clamping brackets to fix all vertical sections to the cross arms<br />
and temporarily align them according to the installation drawing provided.<br />
Note: Tighten the clamping brackets only to a point at which the vertical<br />
sections can still be moved.<br />
Important! The openings of the sections to the very left and right must<br />
face the duct wall.<br />
Push the vertical section to the very left towards the duct roof until it<br />
comes to a stop, then align it at a distance of 50 mm parallel to the duct<br />
wall. Finally, fasten the screws of the respective clamping brackets.<br />
50mm<br />
Hang all drain off sheets into the vertical sections and push them down<br />
to the very stop.<br />
Important! The drain-off sheet with system-specific width (marked with<br />
a “V”) must be mounted in the corresponding interstice (see installation<br />
drawing provided).