02.03.2013 Views

Ikelic - Alliance Digital Repository

Ikelic - Alliance Digital Repository

Ikelic - Alliance Digital Repository

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

STATUS OF OIL SANDS PROJECTS (Underline denotes changes since June 1994)<br />

R&D PROJECTS (Continued)<br />

produced with a disappointing, and unexpected high water cut, whereas no bottom water is known to exist in this particular<br />

area. However, the two subsequent horizontal wells have not had any free water problems. Sand production has not been a<br />

major problem and the production sand content is lower than in surrounding vertical wells.<br />

An additional six horizontal wells were drilled in 1993. To increase reservoir exposure, one of the 1993 wells was drilled and<br />

completed using the lateral tie-back system developed by CS Resources and Sperry-Sun Services. Drilling This system provides<br />

for the complex interconnection of individual production liners, thereby creating total wellbore integrity. The 1993 well drilled<br />

using this system has a total of 2,798 meters of horizontal section. The cost per horizontal meter for this well was $374. The<br />

average drill, case and completion cost of the 1993 wells was $670,000. The wells took an average of 10 days to drill with an<br />

average horizontal section of 1,702 meters. The average cost per horizontal meter for the 1993 wells was $416.<br />

Project Cost: Not disclosed<br />

- PELICAN-WABASCA PROJECT CS<br />

Resources (T-520)<br />

Construction of fireflood and steamflood facilities is complete in the Pelican area of the Wabasca region. Phase I of the<br />

project commenced operations in August 1981, and Phase II (fireflood) commenced operations during September 1982. The<br />

pilot consists of a 31-well centrally enclosed 7-spot pattern plus nine additional wells. Oxygen injection into two of the 7-spot<br />

patterns was initiated in November 1984. Six more wells were added in March 1985 that completed an additional two 7-spot<br />

patterns. In April 1986, the fireflood operation was shut down and the project converted to steam stimulation. Sixteen pilot<br />

wells were cyclic steamed. One pattern was converted to a steam drive, another pattern converted to a water drive. The<br />

remaining wells stayed on production. In January/February 1986, 18 new wells were drilled and put on production.<br />

primary<br />

Cyclic was undertaken steaming in February 1987. The waterflood on the pilot ceased operation in April, 1987. Cyclic steam<br />

ing of the wells producing on the 7-spot steamflood project south of the pilot was converted to steamflood in fall 1987.<br />

In May 1989 all thermal operations had been terminated. The wells were abandoned with the exception of 13 wells that remain<br />

producing on primary production.<br />

The use of horizontal wells is being tested. In 1991, an additional eight horizontal wells were drilled to about 1,000 meters in<br />

length.<br />

Project Cost: Not Specified<br />

- PR SPRING PROJECT Enercor<br />

and Solv-Ex Corporation, (T-540)<br />

The PR Spring Tar Sand Project, a joint venture between Solv-Ex Corporation (the operator) and Enercor, was formed for the<br />

purpose of mining tar sand from leases in the PR Spring area of Utah and extracting the contained hydrocarbon for sale in the<br />

heavy oil markets.<br />

The project's surface mine will utilize a standard box-cut advancing pit concept with a pit area of 20 acres. Approximately<br />

1,600 acres will be mined during the life of the project. Exploratory drilling has indicated oil reserves of 58 million barrels with<br />

an average grade of 7.9 percent weight by bitumen.<br />

The proprietary oil extraction process to be used in the project was developed by Solv-Ex in its laboratories and pilot plant and<br />

claims the advantages of high recovery of bitumen, low water requirements, acceptable environmental effects and low economi<br />

cal capital and costs. operating Process optimization and scale-up testing is currently underway for the Solv-Ex/Shell Canada<br />

Project which uses the same technology.<br />

The extraction plant for the project has been designed to process tar sand ore at a feed rate of 500 tons per hour and produce<br />

net product oil for sale at a rate of 4,663 barrels per day over 330 operating days per year.<br />

In August 1985 the sponsors requested loan and price guarantees totaling $230,947,000 under the United States Synthetic Fuels<br />

Corporation's (SFC's) solicitation for tar sands mining and surface processing projects. On November 19, 1985 the SFC deter<br />

mined that the project was qualified for assistance under the terms of the solicitation. However, the SFC was abolished by<br />

Congress on December 19, 1985 before financial assistance was awarded to the project.<br />

The sponsors are evaluating various product options, including asphalt and combined asphalt/jet fuel. Private financing and<br />

equity participation for the project are being sought.<br />

Project Cost: $158 million (Synthetic crude option)<br />

$90 million (Asphalt option)<br />

3-50<br />

SYNTHETIC FUELS REPORT, JANUARY 1995

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!