- Page 1: CONTRACT DOCUMENTS ANDSPECIFICATION
- Page 5 and 6: Pages03 21 00 Reinforcing Steel ...
- Page 7 and 8: PagesDIVISION 23—HEATING, VENTILA
- Page 9 and 10: PagesDIVISION 40—PROCESS INTEGRAT
- Page 12: TECHNICAL SPECIFICATIONS
- Page 16 and 17: SECTION 01 26 00CONTRACT MODIFICATI
- Page 18 and 19: 1.04 CHANGE ORDERSA. Procedure:1. E
- Page 20 and 21: 6. Leased Equipment, When Idle (Sta
- Page 22 and 23: SECTION 01 29 00PAYMENT PROCEDURESP
- Page 24: 4. Material not unloaded from trans
- Page 27 and 28: C. Contractor shall coordinate dire
- Page 29 and 30: e. Construct new concrete pads for
- Page 31 and 32: d. Reconnect all existing active si
- Page 33 and 34: until connected to new odor control
- Page 35 and 36: C. Engineer shall have the right to
- Page 37 and 38: D. Restore existing work, Undergrou
- Page 39 and 40: 1.04 PROGRESS MEETINGSA. Engineer w
- Page 42 and 43: SECTION 01 32 00CONSTRUCTION PROGRE
- Page 44 and 45: 3. Show complete interdependence an
- Page 46 and 47: Contractor shall, within 7 days of
- Page 48: 1.08 ADJUSTMENT OF CONTRACT TIMESA.
- Page 51 and 52: 3. Identify each submittal with the
- Page 53 and 54:
3. Manufacturer’s Color Chart: Un
- Page 55 and 56:
D. Contract Closeout Submittals: In
- Page 57 and 58:
O. Testing and Startup Data: In acc
- Page 59 and 60:
1. AA Aluminum Association2. AABC A
- Page 61 and 62:
79. MMA Monorail Manufacturers’ A
- Page 64 and 65:
SECTION 01 43 33MANUFACTURERS’ FI
- Page 66 and 67:
3.03 MANUFACTURER’S CERTIFICATE O
- Page 68:
MANUFACTURER’S CERTIFICATE OF COM
- Page 72 and 73:
SECTION 01 45 16.13CONTRACTOR QUALI
- Page 74 and 75:
3.03 QUALITY CONTROL ORGANIZATIONA.
- Page 76 and 77:
d) Establish level of workmanship a
- Page 78 and 79:
D. Notification of Changes: After a
- Page 80:
3.09 COMPLETION INSPECTIONA. CQC Sy
- Page 83 and 84:
2. Special Inspection, Continuous:
- Page 85 and 86:
a. Special Inspection and testing r
- Page 87 and 88:
3.02 TESTINGA. To facilitate testin
- Page 89 and 90:
B. Use area designated for Contract
- Page 91 and 92:
PART 3EXECUTION3.01 ENGINEER’S FI
- Page 93 and 94:
3. Provide means to prevent water u
- Page 95 and 96:
F. Waterways: Keep ditches, culvert
- Page 97 and 98:
3.07 PARKING AREASA. Control vehicu
- Page 99 and 100:
5. U.S. Weather Bureau: Rainfall Fr
- Page 101 and 102:
PART 3EXECUTION3.01 PREPARATIONA. E
- Page 103 and 104:
B. Replace or repair failed or over
- Page 105 and 106:
name of Project and Contractor, equ
- Page 107 and 108:
H. Hazardous Materials: Prevent con
- Page 109 and 110:
B. Lubrication System:1. Require no
- Page 112 and 113:
SECTION 01 64 00OWNER-FURNISHED PRO
- Page 114 and 115:
1.08 EXTRA MATERIALSA. Unless other
- Page 116 and 117:
SECTION 01 77 00CLOSEOUT PROCEDURES
- Page 118 and 119:
B. Preservation:1. Maintain documen
- Page 120 and 121:
SECTION 01 78 23OPERATION AND MAINT
- Page 122 and 123:
1.05 SUBMITTALSA. Informational:d.
- Page 124 and 125:
6. Guarantee, Bond, and Service Agr
- Page 126:
PART 2PART 3PRODUCTS (NOT USED)EXEC
- Page 129 and 130:
Equipment RecordPage 2 of 2Lubrican
- Page 131 and 132:
1.03 FACILITY STARTUP AND PERFORMAN
- Page 133 and 134:
c. Lubricate equipment in accordanc
- Page 135 and 136:
B. Demonstrate proper operation of
- Page 138:
FACILITY PERFORMANCE DEMONSTRATION/
- Page 141 and 142:
G. Universal Waste Lamp: In accorda
- Page 143 and 144:
7. Plug sewer lines with concrete t
- Page 145 and 146:
11. Where the concealed raceway is
- Page 147 and 148:
3.03 BURNING3. Provide protective m
- Page 150 and 151:
SECTION 03 01 32REPAIR OF VERTICAL
- Page 152 and 153:
1.03 SUBMITTALSA. Action Submittals
- Page 154 and 155:
c. Technical representative for rep
- Page 156 and 157:
c. Slant Shear Bond Strength, ASTM
- Page 158 and 159:
3.03 REINFORCEMENT INSTALLATIONA. P
- Page 160 and 161:
B. Compression Strength Test:1. Tes
- Page 162 and 163:
SECTION 03 01 33REPAIR OF HORIZONTA
- Page 164 and 165:
D. New Concrete: Concrete less than
- Page 166 and 167:
E. Freeze-thaw Resistance and Resis
- Page 168 and 169:
I. Manufacturers and Products:1. BA
- Page 170 and 171:
2.08 CEMENTITIOUS BONDING AGENT AND
- Page 172 and 173:
D. Following removal of unsound or
- Page 174 and 175:
c. Working Time: 30 minutes at 70 d
- Page 176 and 177:
2. Direct Tension Bond Test:a. Two
- Page 178 and 179:
SECTION 03 10 00CONCRETE FORMING AN
- Page 180 and 181:
4. Flat bar ties for panel forms; f
- Page 182:
3.03 FORM REMOVALd. Column Type C-A
- Page 185 and 186:
1.02 SUBMITTALSA. Action Submittals
- Page 187 and 188:
2.04 BOND BREAKERA. Tape for Joints
- Page 189 and 190:
H. Ties for PVC Waterstop: “Hog R
- Page 191 and 192:
C. Plastic Waterstop:1. Install in
- Page 193 and 194:
3.07 PREFORMED CONTROL JOINTSA. Use
- Page 195 and 196:
1.02 SUBMITTALSA. Action Submittals
- Page 197 and 198:
2.03 FABRICATIONbe embedded. Precas
- Page 199 and 200:
D. Place welded wire fabric on conc
- Page 201 and 202:
1.02 DEFINITIONSn. C618, Standard S
- Page 203 and 204:
5) Aggregates, including specified
- Page 205 and 206:
B. Qualifications:1. Batch Plant: N
- Page 207 and 208:
c. Limit deleterious substances in
- Page 209 and 210:
7. Use water-reducing and retarding
- Page 211 and 212:
PART 3EXECUTION3.01 PLACING CONCRET
- Page 213 and 214:
4. Consider beams, girders, bracket
- Page 215 and 216:
3. Clean areas to receive grout top
- Page 217 and 218:
4. Inject cracks in accordance with
- Page 219 and 220:
F. Type S-6 (Sidewalk Finish):1. Sl
- Page 221 and 222:
8. If measured air content at deliv
- Page 223 and 224:
3. Bonding Agent Manufacturer’s R
- Page 225 and 226:
3.14 SUPPLEMENTSA. Requirements of
- Page 227 and 228:
Nominal Maximum Aggregate Sizein.
- Page 230 and 231:
CONCRETE MIX DESIGN, CLASS 4500F2S1
- Page 232 and 233:
CONCRETE MIX DESIGN, CLASS SM00F2S1
- Page 234 and 235:
CONCRETE MIX DESIGN, CLASS 4500F1S1
- Page 236 and 237:
CONCRETE MIX DESIGN, CLASS 4500F3S1
- Page 238 and 239:
CONCRETE MIX DESIGN, CLASS GT00F1S1
- Page 240 and 241:
SECTION 03 35 00CONCRETE FINISHINGP
- Page 242 and 243:
3. Sonneborn, Minneapolis, MN.4. Eu
- Page 244 and 245:
SECTION 03 39 00CONCRETE CURINGPART
- Page 246:
B. Use one of the following methods
- Page 249 and 250:
B. Informational Submittals:1. For
- Page 251 and 252:
G. Embedded Items:1. ASTM A36 steel
- Page 253 and 254:
2.05 SOURCE QUALITY CONTROLA. Prepa
- Page 255 and 256:
3.05 FIELD QUALITY CONTROLA. Inspec
- Page 257 and 258:
1.03 QUALIFICATIONS6. Test Reports:
- Page 259 and 260:
B. Category II:1. Nonmetallic, nong
- Page 261 and 262:
7. Strength Test Failures: Nonshrin
- Page 263 and 264:
A. Bagged Material:1. List lot numb
- Page 266 and 267:
SECTION 03 63 00CONCRETE DOWELINGPA
- Page 268 and 269:
c. Simpson Strong-Tie Co., Inc., Pl
- Page 270 and 271:
SECTION 04 21 13.13MASONRY VENEERPA
- Page 272 and 273:
PART 2PRODUCTS2.01 MASONRY UNITSA.
- Page 274 and 275:
G. Sand: ASTM C144, in addition not
- Page 276 and 277:
4. Manufacturer and Product: Dur-O-
- Page 278 and 279:
ick plumb, true to line, with level
- Page 280 and 281:
M. Anchoring: Anchor brick veneer t
- Page 282:
3.07 PROTECTIONA. Wall Covering: Du
- Page 285 and 286:
1.02 SUBMITTALSA. Action Submittals
- Page 287 and 288:
2.02 MASONRY UNITSA. General:1. Fur
- Page 289 and 290:
2.07 GROUT MIXES5. Add remaining ag
- Page 291 and 292:
2. Running Bond:a. Unless otherwise
- Page 293 and 294:
3. Lap reinforcing bars as shown, w
- Page 295 and 296:
. Provide sufficient size to permit
- Page 297 and 298:
E. Protect masonry against freezing
- Page 299 and 300:
J. UT: Ultrasonic Testing.K. VT: Vi
- Page 301 and 302:
3.02 NONDESTRUCTIVE WELD TESTING RE
- Page 304:
Welding and Nondestructive TestingS
- Page 307 and 308:
i. A194/A194M, Specification for Ca
- Page 309 and 310:
E. Submerged: Location at or below
- Page 311 and 312:
ItemSteel Bolts and Nuts:Carbon Ste
- Page 313 and 314:
. Store adhesive cartridges on pall
- Page 315 and 316:
2.10 FLOOR PLATEA. Material:1. Alum
- Page 317 and 318:
2.13 FLOOR HATCHESA. Load Capacity:
- Page 319 and 320:
5. Fabricate to longest length as p
- Page 321 and 322:
2.20 FABRICATIONA. General:1. Finis
- Page 323 and 324:
PART 3EXECUTION3.01 INSTALLATION OF
- Page 325 and 326:
5. Do not exceed maximum torque as
- Page 327 and 328:
3.10 MANUFACTURER’S SERVICESA. Ad
- Page 329 and 330:
Service Useand Location Product Rem
- Page 331 and 332:
c. Design Data: Calculations or tes
- Page 333 and 334:
PART 2PRODUCTS2.01 DESIGN PERFORMAN
- Page 335 and 336:
e. Base Connection:1) Manufacturers
- Page 337 and 338:
B. Bolts and Nuts for Bolting Handr
- Page 339 and 340:
D. Setting Posts:1. Surface Mounted
- Page 342 and 343:
SECTION 05 53 00METAL GRATINGSPART
- Page 344 and 345:
5. Bearing Bars, Cross Bars and Ban
- Page 346:
2. Coordinate dimensions and fabric
- Page 349 and 350:
1.02 SUBMITTALSA. Action Submittals
- Page 351 and 352:
2.03 CONSTRUCTION PANELSA. Plywood:
- Page 353 and 354:
PART 3EXECUTION3.01 EXAMINATIONA. V
- Page 356 and 357:
SECTION 07 19 00WATER REPELLENTSPAR
- Page 358 and 359:
PART 3EXECUTION3.01 EXAMINATION AND
- Page 360 and 361:
SECTION 07 21 00THERMAL INSULATIONP
- Page 362:
3.02 RIGID INSULATIONA. Install in
- Page 365 and 366:
1.02 SUBMITTALSb. HH-I/2, (Basic; A
- Page 367 and 368:
1.07 SPECIAL GUARANTEEA. Product: F
- Page 369 and 370:
2. Flashing sheet combining SBS pol
- Page 371 and 372:
B. Bitumen:1. Maintain kettle tempe
- Page 374 and 375:
SECTION 07 62 00SHEET METAL FLASHIN
- Page 376 and 377:
C. Carefully handle to avoid damage
- Page 378 and 379:
C. Finish: Factory finished with an
- Page 380 and 381:
K. At exposed ends of counterflashi
- Page 382:
3.03 FINISHA. Exposed Surfaces of F
- Page 385 and 386:
D. Manufacturers and Products:1. Pa
- Page 387 and 388:
2.09 ROOF DRAINSA. Molded plastic d
- Page 390 and 391:
SECTION 07 92 00JOINT SEALANTSPART
- Page 392 and 393:
3. Manufacturers and Products:a. BA
- Page 394 and 395:
B. Joint Cleaner: Noncorrosive and
- Page 396 and 397:
C. Apply joint sealant manufacturer
- Page 398:
SECTION 08 06 01DOOR AND HARDWARE S
- Page 404 and 405:
SECTION 08 11 16ALUMINUM DOORS AND
- Page 406:
PART 3EXECUTION3.01 INSTALLATIONA.
- Page 409 and 410:
B. Informational Submittals:1. Thir
- Page 411 and 412:
2.04 FINISHES4. Motor Rating: Minim
- Page 414 and 415:
SECTION 08 41 13ALUMINUM-FRAMED ENT
- Page 416 and 417:
PART 2PRODUCTS2.01 MANUFACTURERSA.
- Page 418 and 419:
3.02 INSTALLATIONA. In accordance w
- Page 420 and 421:
SECTION 08 71 00DOOR HARDWAREPART 1
- Page 422 and 423:
Door HeightUp to 5'-0”5'-1” to
- Page 424 and 425:
2.07 EXIT DEVICESA. BHMA A156.3.B.
- Page 426 and 427:
No. Type Description Pemko ReeseT2
- Page 428:
3.03 MANUFACTURER’S SERVICESA. De
- Page 431 and 432:
1.02 SUBMITTALSp. E1300, Standard P
- Page 433 and 434:
B. Handling:1. Stack individual lit
- Page 435 and 436:
1. Silicone Glazing Sealant: ASTM C
- Page 437 and 438:
B. Exterior Dry Method (Gasket Glaz
- Page 440 and 441:
SECTION 08 90 00LOUVERSPART 1GENERA
- Page 442 and 443:
2.03 ACCESSORIESA. Anchors and Fast
- Page 444:
LOUVER SCHEDULELOUVER TYPES: ABBREV
- Page 448 and 449:
INTERIOR FINISH SCHEDULEABBREVIATIO
- Page 450 and 451:
SECTION 09 90 00PAINTING AND COATIN
- Page 452 and 453:
3. Factory Applied Coatings: Manufa
- Page 454 and 455:
2.03 PAINT MATERIALSA. General:1. M
- Page 456 and 457:
d. Prior to blast cleaning, grind s
- Page 458 and 459:
more than 5 percent of each unit ar
- Page 460 and 461:
4. Brush-off blast clean to remove
- Page 462 and 463:
c. Acid will react vigorously for a
- Page 464 and 465:
4. Visually inspect concrete, mason
- Page 466 and 467:
G. System No. 25 Exposed PVC:Surfac
- Page 468 and 469:
pinholes, holidays, and discontinui
- Page 470:
PAINT SYSTEM DATA SHEETComplete thi
- Page 474 and 475:
SECTION 10 14 00SIGNAGEPART 1GENERA
- Page 476 and 477:
2.04 SIGNSC. Manufacturers and Prod
- Page 478 and 479:
6. Manufacturers and Products:a. Br
- Page 480 and 481:
MarkMaterialH-3 CalciumHydroxide (9
- Page 482:
3.07 SUPPLEMENTS2. Operating Proced
- Page 485 and 486:
SIGN SCHEDULESignSize Mounting Lett
- Page 488 and 489:
SECTION 10 44 00PORTABLE FIRE AND S
- Page 490:
PART 3EXECUTION3.01 INSTALLATIONA.
- Page 494 and 495:
SECTION 22 10 01.08POLYETHYLENE (PE
- Page 496 and 497:
SECTION 22 40 00PLUMBING FIXTURESPA
- Page 498 and 499:
4. FD-2, Floor Drain (Unfinished Ar
- Page 500:
D. Adjust water flows in domestic w
- Page 503 and 504:
4. Have a proven record of at least
- Page 505 and 506:
4. Adjust outside air dampers, retu
- Page 508 and 509:
SECTION 23 09 00.01HVAC CONTROLS SE
- Page 510 and 511:
SECTION 23 09 13HVAC CONTROLS, FIEL
- Page 512 and 513:
SECTION 23 31 13METAL DUCTS AND ACC
- Page 514 and 515:
1.02 DEFINITIONSd. Fire, Smoke, and
- Page 516 and 517:
E. Changes or alterations to layout
- Page 518 and 519:
D. Water-Based Sealants:1. Listed b
- Page 520 and 521:
2. Provide fasteners that do not da
- Page 522 and 523:
2.10 MANUAL DAMPERSA. Butterfly Man
- Page 524 and 525:
C. Penetrations:1. Provide duct sle
- Page 526 and 527:
D. Support horizontal ducts within
- Page 528:
3.09 BALANCING OF AIR SYSTEMSA. Per
- Page 531 and 532:
e. Drawings showing layout, support
- Page 533 and 534:
B. Reinforcement:1. Veil: Chemical
- Page 535 and 536:
3. Support Spacing:a. 24 Inch Diame
- Page 537 and 538:
6. Anti-seize thread compound shall
- Page 539 and 540:
4. 1-inch minimum flat rectangular
- Page 541 and 542:
1.02 DEFINITIONS6. CSA America (CSA
- Page 543 and 544:
d) Static pressure, capacity, horse
- Page 545 and 546:
PART 2PRODUCTS2.01 EQUIPMENT SCHEDU
- Page 547 and 548:
2. Panel Arrangement: Panels mechan
- Page 549 and 550:
5) Base:a) All-welded heavy-gauge m
- Page 551 and 552:
d. Adequately sized access door(s)
- Page 553 and 554:
H. Control Dampers:1. Internally mo
- Page 555 and 556:
2.08 CORROSION PROTECTIONA. General
- Page 557 and 558:
a. Belt Drive (except Vane Axial):
- Page 559 and 560:
E. Vibration Testing:3.04 CLEANING1
- Page 561 and 562:
AIR HANDLING UNITSEQUIPMENT ID NUMB
- Page 563 and 564:
1.02 DEFINITIONSA. The following is
- Page 565 and 566:
PART 2PRODUCTS2.01 GENERALA. Specif
- Page 567 and 568:
5. Low pressure bypass shall be fac
- Page 569 and 570:
C. Coating Process:1. Coil Inspecti
- Page 571 and 572:
supervise initial operation, calibr
- Page 574:
WALL MOUNT AIR CONDITIONER 23 81 00