31.07.2015 Views

Vol 2 - Garney Construction

Vol 2 - Garney Construction

Vol 2 - Garney Construction

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

e. Construct new concrete pads for new Owner provided loopswitches and transformers.f. Mount new Owner-provided loop switches and transformers.g. Install primary conductors between loop switches andtransformers.h. Construct new concrete pad and install the temporary servicedisconnect switch.i. Install temporary conductors between new Transformer T2 totemporary service disconnect, and between the temporary servicedisconnect and Side A of existing MCC-9.j. Power the Final Basin Pump Station from Transformer T9 andSettled Sewage Pump Station from Transformer T10.k. Remove existing primary conductors from the main 12.47 KVswitchgear to existing T2 loop switch, and from existing T2 loopswitch to existing T3 loop switch.l. Install new primary conductors from the main 12.47 KVswitchgear to new T2 loop switch, and from new T2 loop switchto existing T3 loop switch.m. Power the Solids Processing Building from new Transformer T2,the Final Basin Pump Station from Transformer T3 and SettledSewage Pump Station form Transformer T4.n. Remove the existing loop switches for both T2 and T8 andassociated ductbanks.o. Remove existing Transformer T8 and associated ductbank.p. Remove existing primary conductors from the main 12.47 KVswitchgear to existing T8 loop switch, and from existing T8 loopswitch to existing T9 loop switch.q. Install new primary conductors from the main 12.47 KVswitchgear to new T8 loop switch, and from new T8 loop switchto existing T9 loop switch.r. Power the Solids Processing Building from new Transformers T2,the Final Basin Pump Station from both Transformers T3 and T9and Settled Sewage Pump Station from both Transformers T4 andT10.3. Electrical Room Addition and Low <strong>Vol</strong>tage Switchgear - Milestone 2(240 Days from Notice to Proceed):a. Prior to commencing construction activities associated with thenew Electrical Room, Contractor shall complete the following:1) Complete all Work under Milestone 1.2) Either temporarily relocate existing MAU-7005 to providecontinued heating/ventilation to the Belt Filter Press Roomor remove MAU-7005 and provide temporary heating /ventilation of equivalent capacity (minimum six air changesPROJECT COORDINATIONPW/WBG/38205901 31 13 - 4 AUGUST 15, 2012©COPYRIGHT 2012 CH2M HILL

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!