- three circular steel-lined Pressure Shafts, each <strong>of</strong> 4.9 m. dia. and 633 m. long bifurcating<br />

near the <strong>Power</strong> House to feed six generating units.<br />

- an underground <strong>Power</strong> House with a cavern size <strong>of</strong> 222 m. x 20 m. x 49 m. having six<br />

Francis Units <strong>of</strong> 250 MW each to utilise a design discharge <strong>of</strong> 405 cusecs and design<br />

head <strong>of</strong> 425 m.<br />

- a 10.15 m. dia. and 982 m. long Tail Race Tunnel to discharge the water back into the<br />

river Satluj.<br />

11.8.3 PROJECT BENFITS:<br />

Besides the social and economical upliftment <strong>of</strong> the persons in its vicinity, on<br />

commissioning the 1500 MW NJHEP will generate 6700 MUs <strong>of</strong> the electrical energy<br />

in a 90% dependable year and 7447 MU in an average year, besides providing 1500<br />

MW <strong>of</strong> valuable peaking power to the Northern Grid.<br />

11.8.4 Utilisation <strong>of</strong> Resources during 1<strong>99</strong>7-98<br />

Against the Revised Estimates <strong>of</strong> Rs.887 crores for the year 1<strong>99</strong>7-98, expenditure<br />

incurred during the year was Rs.672 crores. Out <strong>of</strong> total World Bank Loan <strong>of</strong> Rs.1573<br />

crores (US $ 437 Million), NJPC has utilised Rs.921 crores (US $ 258 Million). During<br />

the year, a sum <strong>of</strong> Rs.171 crores has been utilised, against a target <strong>of</strong> Rs.240 crores.<br />

11.8.5 PROJECT EXECUTION STATUS:<br />

HIGHLIGHTS: PROJECT EXECUTION<br />

- Daylighting in the HRT between Wadhal D/S - Manglad U/S and Manglad D/S -<br />

Rattanpur U/S.<br />

- Widening <strong>of</strong> Pressure Shafts I to III completed<br />

- Satluj river diverted through the diversion tunnel.<br />

- Dental concreting in the Dam area commenced in January, <strong>1<strong>99</strong>8</strong>.<br />

- Out <strong>of</strong> 27.40 km. <strong>of</strong> the HRT, excavation (Heading) <strong>of</strong> 23.80 km. completed upto end<br />

<strong>of</strong> January, <strong>1<strong>99</strong>8</strong>.<br />

- Erection <strong>of</strong> steel liners in the HRT at Manglad D/S commenced in March, 1<strong>99</strong>7.<br />

- Excavation <strong>of</strong> power house cavern completed in December, 1<strong>99</strong>6<br />

- Excavation <strong>of</strong> TRT completed in February, 1<strong>99</strong>7.<br />

- Erection <strong>of</strong> steel liners in top horizontal portion <strong>of</strong> the pressure shaft No.2 & 3 completed<br />

in February, 1<strong>99</strong>7.<br />

- Tail Race Tunnel concrete lining commenced in March, 1<strong>99</strong>7.<br />

- Concreting <strong>of</strong> draft tubes for units I to IV completed.<br />

- Concrete lining <strong>of</strong> Lower Expansion Gallery <strong>of</strong> Surge Shaft was completed during<br />

July, 1<strong>99</strong>7.<br />

108