- three circular steel-lined Pressure Shafts, each <strong>of</strong> 4.9 m. dia. and 633 m. long bifurcating<br />
near the <strong>Power</strong> House to feed six generating units.<br />
- an underground <strong>Power</strong> House with a cavern size <strong>of</strong> 222 m. x 20 m. x 49 m. having six<br />
Francis Units <strong>of</strong> 250 MW each to utilise a design discharge <strong>of</strong> 405 cusecs and design<br />
head <strong>of</strong> 425 m.<br />
- a 10.15 m. dia. and 982 m. long Tail Race Tunnel to discharge the water back into the<br />
river Satluj.<br />
11.8.3 PROJECT BENFITS:<br />
Besides the social and economical upliftment <strong>of</strong> the persons in its vicinity, on<br />
commissioning the 1500 MW NJHEP will generate 6700 MUs <strong>of</strong> the electrical energy<br />
in a 90% dependable year and 7447 MU in an average year, besides providing 1500<br />
MW <strong>of</strong> valuable peaking power to the Northern Grid.<br />
11.8.4 Utilisation <strong>of</strong> Resources during 1<strong>99</strong>7-98<br />
Against the Revised Estimates <strong>of</strong> Rs.887 crores for the year 1<strong>99</strong>7-98, expenditure<br />
incurred during the year was Rs.672 crores. Out <strong>of</strong> total World Bank Loan <strong>of</strong> Rs.1573<br />
crores (US $ 437 Million), NJPC has utilised Rs.921 crores (US $ 258 Million). During<br />
the year, a sum <strong>of</strong> Rs.171 crores has been utilised, against a target <strong>of</strong> Rs.240 crores.<br />
11.8.5 PROJECT EXECUTION STATUS:<br />
HIGHLIGHTS: PROJECT EXECUTION<br />
- Daylighting in the HRT between Wadhal D/S - Manglad U/S and Manglad D/S -<br />
Rattanpur U/S.<br />
- Widening <strong>of</strong> Pressure Shafts I to III completed<br />
- Satluj river diverted through the diversion tunnel.<br />
- Dental concreting in the Dam area commenced in January, <strong>1<strong>99</strong>8</strong>.<br />
- Out <strong>of</strong> 27.40 km. <strong>of</strong> the HRT, excavation (Heading) <strong>of</strong> 23.80 km. completed upto end<br />
<strong>of</strong> January, <strong>1<strong>99</strong>8</strong>.<br />
- Erection <strong>of</strong> steel liners in the HRT at Manglad D/S commenced in March, 1<strong>99</strong>7.<br />
- Excavation <strong>of</strong> power house cavern completed in December, 1<strong>99</strong>6<br />
- Excavation <strong>of</strong> TRT completed in February, 1<strong>99</strong>7.<br />
- Erection <strong>of</strong> steel liners in top horizontal portion <strong>of</strong> the pressure shaft No.2 & 3 completed<br />
in February, 1<strong>99</strong>7.<br />
- Tail Race Tunnel concrete lining commenced in March, 1<strong>99</strong>7.<br />
- Concreting <strong>of</strong> draft tubes for units I to IV completed.<br />
- Concrete lining <strong>of</strong> Lower Expansion Gallery <strong>of</strong> Surge Shaft was completed during<br />
July, 1<strong>99</strong>7.<br />