(viii) A pilot project for installation <strong>of</strong> 500 Electric Meters with Time-<strong>of</strong>-the-Day (TOD)<br />
facility, sanctioned in February, 1<strong>99</strong>7 for contribution <strong>of</strong> Rs.88 lakh (50% <strong>of</strong> the<br />
total cost) is under implementation by the West Bengal State Electricity Board in<br />
respect <strong>of</strong> the HT consumers. The installation <strong>of</strong> meters and other necessary<br />
equipment is scheduled to be completed in 18 months.<br />
(ix) A project for implementation <strong>of</strong> the recommendations <strong>of</strong> the Energy Audit Report<br />
on Shakti Bhavan Complex, Lucknow <strong>of</strong> UPSEB, sanctioned in March, 1<strong>99</strong>7 for<br />
contribution <strong>of</strong> Rs.13.485 lakh (50% <strong>of</strong> the total cost) is under implementation<br />
by UPSEB. The project has a completion schedule <strong>of</strong> 11 months.<br />
(x) A Project for power generation through waste heat recovery from existing nonrecovery<br />
coke ovens in and around Dhanbad area, sanctioned in March, 1<strong>99</strong>7 for<br />
contribution <strong>of</strong> Rs.4.25 lakh (85% <strong>of</strong> the total cost), is under implementation<br />
through Central Fuel Research Institute (CFRI), Dhanbad. The project has a<br />
completion schedule <strong>of</strong> 10 months.<br />
(xi) A project for replacement <strong>of</strong> incandescent bulbs by Compact Fluorescent Lamps<br />
(CFLs) in Leh has been sanctioned in October, 1<strong>99</strong>7 for contribution <strong>of</strong> Rs.2.10<br />
lakh (50% <strong>of</strong> the total cost) for implementation by Ladakh Autonomous Hill<br />
Development Council (LAHDC). The project has a completion schedule <strong>of</strong> 6<br />
months.<br />
10.3.3 Other Projects for Energy Conservation in Transmission & Distribution<br />
(i) The project for setting up <strong>of</strong> Energy Meter Testing Facility, sanctioned in January,<br />
1<strong>99</strong>4 at a cost <strong>of</strong> Rs.69.96 lakh (revised to Rs.86.51 lakh in September, 1<strong>99</strong>5) has<br />
been successfully completed by the Central <strong>Power</strong> Research Institute (CPRI) in<br />
1<strong>99</strong>7-98.<br />
(ii) The R&D project on reduction <strong>of</strong> losses in electricity distribution system through<br />
suitable capacitors using a Solid State Switch, sanctioned in December, 1<strong>99</strong>5 for<br />
a contribution <strong>of</strong> Rs.10 lakh, is under implementation through the Electrical<br />
Research & Development Association (ERDA), Vadodara. The project is expected<br />
to be completed by December, <strong>1<strong>99</strong>8</strong>.<br />
(iii) The R&D project on development <strong>of</strong> integrated energy efficient Stirling engine<br />
Battery/Inverter System for Remote Area <strong>Power</strong> Generation sanctioned in March,<br />
1<strong>99</strong>5 for a contribution <strong>of</strong> Rs.23.20 lakh, is under implementation by the Central<br />
<strong>Power</strong> Research Institute (CPRI). The project is expected to be completed by<br />
December, <strong>1<strong>99</strong>8</strong>.<br />