CHAPTER - V<br />
APPRAISAL REPORT OF MAJOR PROJECTS/PROGRAMMES<br />
This chapter attempts to outline the progress made in execution <strong>of</strong> major projects<br />
involving substantial investments. The following aspects <strong>of</strong> projects/programmes having<br />
an estimated outlay exceeding Rs.100 crore, are highlighted:-<br />
i) Original Estimated Cost;<br />
ii) Revised Estimated Cost;<br />
iii) Specific reasons/factors responsible for revision in the cost;<br />
iv) Schedule <strong>of</strong> commissioning/completion (original & revised);<br />
v) Year-wise performance details in terms <strong>of</strong> financial and physical progress targetted<br />
and achieved; and<br />
vi) Details <strong>of</strong> performance <strong>of</strong> projects in their operation phase.<br />
The Project-wise status <strong>of</strong> construction activities undertaken by various Corporations<br />
are as under:-<br />
1. NATIONAL HYDRO ELECTRIC POWER CORPORATION (NHPC)<br />
1.1 Uri H.E. Project (4x 120 M.W.)<br />
Uri Project in Baramulla District <strong>of</strong> J&K envisages harnessing tail water <strong>of</strong> the existing<br />
Lower Jhelam H.E. Project. The installed capacity <strong>of</strong> the project is 480 MW. The annual<br />
design Energy <strong>of</strong> this project is 2663 M.U. The project was executed by N.H.P.C. with<br />
foreign tie-up for part financing the cost. A turnkey contract for construction <strong>of</strong> the<br />
project with a Swedish-British Consortium was entered in October, 1989 for completion<br />
<strong>of</strong> the project in 72 months. Some time over-run became inevitable due to disturbed<br />
condition around the work site. All the four units <strong>of</strong> this project have been commissioned<br />
on 27.01.97, 03.03.97, 13.03.97 and 10.06.97 and are in commercial generation since<br />
June, 1<strong>99</strong>7. Against the target <strong>of</strong> 1500 MUs the project has generated 2170.94 MUs in<br />
1<strong>99</strong>7-98. The likely completion cost <strong>of</strong> the project will be around Rs. 3300 crores as<br />
against original estimate <strong>of</strong> Rs. 1632.62 crores. The increase in the estimated cost is<br />
mainly on account <strong>of</strong> exchange rate variation, price escalation, statutory reason and<br />
Financing Charges etc.<br />
1.2 Dulhasti H.E. Project (3 x 130 M.W.)<br />
Dulhasti hydro-electric project, is a run <strong>of</strong> the river scheme located on the river Chenab<br />
in Jammu & Kashmir. The installed capacity <strong>of</strong> the project is 390 M.W. with estimated<br />