generating equipment etc. have been placed on M/s. BHEL. The tenders for electrical<br />

works have been received and are under technical evaluation.<br />

It is a fixed price contract <strong>of</strong> Rs.273.01 crore at March, 94 price level + 15% contingency<br />

on civil works amounting to Rs.24.4 crore. The project is scheduled for completion by<br />

September, 2001.<br />

1.6 OTHER PROJECTS:<br />

NHPC has two other projects under consideration, viz., Koel Karo (710 MW) in Bihar<br />

and Chamera Project Stage-II (300 MW) in Himachal Pradesh.<br />

i) Koel-Karo H.E. Project (4 x 172.5 M.W.)<br />

710 MW Koel Karo H.E. Project located in Ranchi, Gumla and Singbhum districts <strong>of</strong><br />

Bihar, envisages regulation <strong>of</strong> the waters <strong>of</strong> South Koel and North Karo rivers for<br />

generating 1000 MUs <strong>of</strong> energy at 16% load factor. The scheme envisages construction<br />

<strong>of</strong> four units <strong>of</strong> 172.5 M.W. each totalling 690 MW. In order to utilise the drop in trans<br />

basin channel, an additional surface power house containing a single unit <strong>of</strong> 20 MW is<br />

envisaged at Raitoli making the total installed capacity <strong>of</strong> the scheme as 710 MW. The<br />

power evacuation system would comprise a 400 KV S/C 200 KM Transmission Line<br />

from Koel Karo to Jamshedpur.<br />

The project was approved by the Government in November, 1<strong>99</strong>1. The approved cost<br />

for generation portion <strong>of</strong> the project was Rs.1286.22 crore including IDC <strong>of</strong> Rs.195.68<br />

crore (at March,’91 price level). Latest revised cost <strong>of</strong> the project is Rs.2624.29 crore<br />

(at Aug.,’96 price level). The actual expenditure on the project till March,’98 is Rs.21.53<br />

crore.<br />

Work <strong>of</strong> the project could not be started due to paucity <strong>of</strong> funds and local resistance.<br />

The project was posed to OECF for their financial assistance during 1<strong>99</strong>6-97 and details<br />

<strong>of</strong> the project execution were presented to OECF Fact Finding Mission. The response<br />

from the OECF in the matter has not been favourable. Document for World Bank funding<br />

for this project is under consideration.<br />

ii) Chamera Stage-II:<br />

Chamera H.E. Project Stage-II located in Chamba Distt. <strong>of</strong> Himachal Pradesh plans to<br />

utilise power potential <strong>of</strong> river Ravi. The project envisages construction <strong>of</strong> a 39 m.<br />

high concrete dam, 7.86 km. long (7m. dia) Head Race Tunnel, 95 m. high (15.5. m.<br />

dia) surge shaft, a circular steel lined pressure shaft <strong>of</strong> 5.1 m. in diameter with an<br />

underground power house accommodating 3x100 MW generating units and a 3.6 km.<br />

long (7 m. dia) tail race tunnel and is expected to generate 1270 MUs <strong>of</strong> energy per<br />

annum.<br />