instructions for suspending the activities <strong>of</strong> blasting and movement <strong>of</strong> vehicles in the<br />

dam area. Because <strong>of</strong> these restrictions about two and a half months <strong>of</strong> the working<br />

season has been lost.<br />

Progress achieved till March,’98 is as under:<br />

i) Core stripping : 1014.92 Th. Cu. m.<br />

ii) Placement <strong>of</strong> Shell : 128.90 Th. Cu. m.<br />

iii) Stock Piling <strong>of</strong> Clay : 302.80 Th. Cu. m.<br />

iv) Top Soil Removal : 585.77 RM.<br />

v) Excavation <strong>of</strong> underground galaries : 369.15 Th. Cu. m.<br />

B) POWER HOUSE: The work at various cavities, adits and drainage galleries is in progress<br />

in the three packages:<br />

i) Package-I: Open excavation in the control gate shaft area had been in progress. The total<br />

quantity excavated so far is 771.50 Th. Cu. m. till March,’98.<br />

Underground excavation for cavities <strong>of</strong> Butterfly Valve Chamber and Penstock<br />

Assembly Chamber is continuing. The cumulative excavation done is 21.28 Th.Cu.m.<br />

and 23.21 Th.Cu.m. in these two cavities respectively till March’98. Excavation for<br />

lower horizontal pressure shafts and penstock No. 1, 2 & 3 has been completed.<br />

Excavation <strong>of</strong> pilot shaft for 110 m. deep vertical Penstocks No. 1 & 4 have been<br />

completed and further widening <strong>of</strong> Penstock no. 1 has been taken up.<br />

ii) Package-II: Underground excavation <strong>of</strong> Machine Hall and Transformer Hall caverns and<br />

Crane beam casting in Machine Hall are the major activities. The total excavation <strong>of</strong> 82.84 &<br />

59.24 Th. Cu. m. have been achieved in these caverns so far respectively. The work <strong>of</strong> crane<br />

beam casting is nearing completion.<br />

In addition 561.10 RM <strong>of</strong> underground excavation in Drainage Galleries has been carried<br />

out till March,’98. The excavation in expansion chamber is in progress and total quantity<br />

excavated so far is 6.04 Th.Cu.m.<br />

iii) Package-III: Underground excavation for tail race tunnels TRT-1 & TRT-2 is in progress.<br />

The total quantity excavated so far is 612.0 RM and 540.0 RM respectively in TRT-1 &<br />

TRT-2. The cumulative quantity <strong>of</strong> open excavation work at TRT’s portals stands at 175.90<br />

Th.Cu.m.<br />

C) CONTRACTS:<br />

i) Spillway: Techno-commercial bids submitted by the prequalified parties have been opened<br />

and construction methodology based on Technical Advisory Committee observations have<br />

been finalised. The Techno-commercial evaluation is in process.<br />