Detailed soil investigation work has already been completed. Land acquisition is in<br />
progress, 368 acres <strong>of</strong> Govt. land has already been acquired whereas balance land is<br />
expected to be handed over by State Govt. shortly. The bids for Main Plant Turnkey<br />
Package have been opened on 11.03.98. Various infrastructure activities are taken up<br />
at the site. The first unit <strong>of</strong> the project is scheduled to be commissioned in March 2002<br />
and the second unit in December 2002.<br />
The entire power generated by this project will be supplied to Andhra Pradesh State as<br />
per power purchase agreement signed between NTPC and APSEB (Andhra Pradesh<br />
State Electricity Board).<br />
3. POWERGRID CORPORATION OF INDIA LIMITED<br />
3.1 NATHPA - JHAKRI TRANSMISSION SYSTEM<br />
The Nathpa-Jhakri Transmission System was approved in April 1989. The World Bank<br />
assistance is available for this project. The Transmission System has been planned for<br />
completion in three stages.<br />
Construction <strong>of</strong> Bawana-Hissar & Hissar-Jaipur Transmission lines and sub station<br />
have been completed, Work at Hissar, Nallagarh, Abdullapur & Bawana sub-station<br />
are in progress. Foundation, tower erection and stinging work are in progress. Due to<br />
non availability <strong>of</strong> construction date <strong>of</strong> Koldam, Line is being terminated at Nallgarh<br />
where a 400/220 KV substation is being constructed. Later on line would be LILO with<br />
Koldam. Jhakri - Nallagarh and Jhakri - Abdullapur lines are expected to be completed<br />
by 10/<strong>99</strong>. Whereas the Nallagarh- Hissar and Abdullapur - Bawana lines are expected<br />
to be completed by 03/<strong>99</strong>.<br />
3.2 DULHASTI TRANSMISSION SYSTEM<br />
The contingency system comprising <strong>of</strong> 220 KV D/C Dulhasti-Kishenpur line & 400/<br />
220 KV sub-station at Kishtwar was prepared to evacuate power from Dulhasti HE<br />
Project. Since Dulhasti <strong>Power</strong> Project is delayed and anticipated in 2002, 220 KV D/C<br />
line has been upgraded to 400 KV S/C line and Kistwar sub station is deleted. However,<br />
supplies which have already taken /manufactured are being diverted to other projects.<br />
The transmission line construction is awarded on Turnkey basis. All <strong>of</strong> the bay equipment<br />
are awarded. Foundation & Tower erection and stringing work are in progress.<br />
Amendment for upgradation scheme has been released in 10/95. Tower and Line<br />
materials supply is almost completed. The project is expected to be commissioned in<br />
June 1<strong>99</strong>9.<br />