04.08.2013 Views

PERFORMANCE BUDGET 1998-99 - Ministry of Power

PERFORMANCE BUDGET 1998-99 - Ministry of Power

PERFORMANCE BUDGET 1998-99 - Ministry of Power

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

1398 m.(90%) tunnel excavation from upstream and 100%(434 m.) from down stream<br />

has also been completed. Benching <strong>of</strong> desilting chambers is in progress. Excavation<br />

and concrete lining <strong>of</strong> surge shaft has also been completed. Excavation <strong>of</strong> 110 m. deep<br />

pressure shaft and concreting <strong>of</strong> 3 nos. penstocks has also been completed. Erection <strong>of</strong><br />

steel liner for horizontal and vertical portion <strong>of</strong> pressure shaft has been completed in a<br />

length <strong>of</strong> 103m. (36%) out <strong>of</strong> the total length <strong>of</strong> 278 m. The actual expenditure on this<br />

project till March,’98 is Rs.268.42 crore. The project is scheduled for completion by<br />

March 1<strong>99</strong>9.<br />

1.4 Dhauliganga Project Stage 1 (4 x 70 M.W.)<br />

Dhauliganga HE Project Stage-I located in Uttar Pradesh is to be constructed on river<br />

Dhauliganga which is a tributary <strong>of</strong> river Kali for an installed capacity <strong>of</strong> 280 MW. The<br />

estimated annual generation <strong>of</strong> power from this project is 1134 MU. The project was<br />

approved in April, 1<strong>99</strong>1 with an estimated cost <strong>of</strong> Rs.601.98 crore. Considering loan<br />

assistance <strong>of</strong> 5665 M Yen (Rs.211 crore) under OECF Annual ODA Plan 1<strong>99</strong>5-96,<br />

anticipated completion cost <strong>of</strong> the project has been revised at 4/95 exchange rate which<br />

works out to Rs.1881.49 crore. Meanwhile, an international consultant as per the<br />

conditions <strong>of</strong> OECF loan, has been appointed in June, 97 to assist NHPC for review<br />

and finalisation <strong>of</strong> feasibility report, preparation <strong>of</strong> tender documents for major works<br />

and award there<strong>of</strong>. The consultant has submitted final report <strong>of</strong> the reviewed feasibility<br />

report <strong>of</strong> Phase-I which is under examination. Phase-II <strong>of</strong> the consultancy services has<br />

started. Also at the project, work is going on for development <strong>of</strong> internal roads, benches<br />

for facilities, besides temporary and permanent housing and <strong>of</strong>fice facilities. The work<br />

<strong>of</strong> major components is likely to be awarded by May, <strong>99</strong> as per the current<br />

implementation schedule. OECF has further sanctioned 16,316 million yen under the<br />

second tranche for implementation <strong>of</strong> major works package under ODA plan <strong>1<strong>99</strong>8</strong>-<strong>99</strong><br />

for which the loan agreement was signed on 30.12.97. The project is scheduled to be<br />

completed by Sep. 2004.<br />

1.5 Kurichu H.E. Project (3 x 15 M.W.)<br />

NHPC has been entrusted with the execution <strong>of</strong> Kurichu H.E. Project in Bhutan and an<br />

agreement was signed between Kurichu Project Authority & N.H.P.C. on 27.9.95 in<br />

this regard. Land acquisition and development <strong>of</strong> infrastructure are in progress at the<br />

project. The diversion tunnel has been daylighted on 14.11.97 successfully and benching<br />

activity has been completed. Concrete lining <strong>of</strong> diversion tunnel has been started and<br />

78 m. progress has been achieved. The excavation <strong>of</strong> left abutment <strong>of</strong> Dam and<br />

realigment <strong>of</strong> road beyond dam axis has been done by NHPC and a progress <strong>of</strong> 82,000<br />

cum. has been achieved. Excavation works <strong>of</strong> power house to the extent <strong>of</strong> 62,000<br />

cum. out <strong>of</strong> a total 90,000 cum. has been completed. The orders for supply <strong>of</strong> main<br />

113

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!