PERFORMANCE BUDGET 1998-99 - Ministry of Power
PERFORMANCE BUDGET 1998-99 - Ministry of Power
PERFORMANCE BUDGET 1998-99 - Ministry of Power
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
1398 m.(90%) tunnel excavation from upstream and 100%(434 m.) from down stream<br />
has also been completed. Benching <strong>of</strong> desilting chambers is in progress. Excavation<br />
and concrete lining <strong>of</strong> surge shaft has also been completed. Excavation <strong>of</strong> 110 m. deep<br />
pressure shaft and concreting <strong>of</strong> 3 nos. penstocks has also been completed. Erection <strong>of</strong><br />
steel liner for horizontal and vertical portion <strong>of</strong> pressure shaft has been completed in a<br />
length <strong>of</strong> 103m. (36%) out <strong>of</strong> the total length <strong>of</strong> 278 m. The actual expenditure on this<br />
project till March,’98 is Rs.268.42 crore. The project is scheduled for completion by<br />
March 1<strong>99</strong>9.<br />
1.4 Dhauliganga Project Stage 1 (4 x 70 M.W.)<br />
Dhauliganga HE Project Stage-I located in Uttar Pradesh is to be constructed on river<br />
Dhauliganga which is a tributary <strong>of</strong> river Kali for an installed capacity <strong>of</strong> 280 MW. The<br />
estimated annual generation <strong>of</strong> power from this project is 1134 MU. The project was<br />
approved in April, 1<strong>99</strong>1 with an estimated cost <strong>of</strong> Rs.601.98 crore. Considering loan<br />
assistance <strong>of</strong> 5665 M Yen (Rs.211 crore) under OECF Annual ODA Plan 1<strong>99</strong>5-96,<br />
anticipated completion cost <strong>of</strong> the project has been revised at 4/95 exchange rate which<br />
works out to Rs.1881.49 crore. Meanwhile, an international consultant as per the<br />
conditions <strong>of</strong> OECF loan, has been appointed in June, 97 to assist NHPC for review<br />
and finalisation <strong>of</strong> feasibility report, preparation <strong>of</strong> tender documents for major works<br />
and award there<strong>of</strong>. The consultant has submitted final report <strong>of</strong> the reviewed feasibility<br />
report <strong>of</strong> Phase-I which is under examination. Phase-II <strong>of</strong> the consultancy services has<br />
started. Also at the project, work is going on for development <strong>of</strong> internal roads, benches<br />
for facilities, besides temporary and permanent housing and <strong>of</strong>fice facilities. The work<br />
<strong>of</strong> major components is likely to be awarded by May, <strong>99</strong> as per the current<br />
implementation schedule. OECF has further sanctioned 16,316 million yen under the<br />
second tranche for implementation <strong>of</strong> major works package under ODA plan <strong>1<strong>99</strong>8</strong>-<strong>99</strong><br />
for which the loan agreement was signed on 30.12.97. The project is scheduled to be<br />
completed by Sep. 2004.<br />
1.5 Kurichu H.E. Project (3 x 15 M.W.)<br />
NHPC has been entrusted with the execution <strong>of</strong> Kurichu H.E. Project in Bhutan and an<br />
agreement was signed between Kurichu Project Authority & N.H.P.C. on 27.9.95 in<br />
this regard. Land acquisition and development <strong>of</strong> infrastructure are in progress at the<br />
project. The diversion tunnel has been daylighted on 14.11.97 successfully and benching<br />
activity has been completed. Concrete lining <strong>of</strong> diversion tunnel has been started and<br />
78 m. progress has been achieved. The excavation <strong>of</strong> left abutment <strong>of</strong> Dam and<br />
realigment <strong>of</strong> road beyond dam axis has been done by NHPC and a progress <strong>of</strong> 82,000<br />
cum. has been achieved. Excavation works <strong>of</strong> power house to the extent <strong>of</strong> 62,000<br />
cum. out <strong>of</strong> a total 90,000 cum. has been completed. The orders for supply <strong>of</strong> main<br />
113