11. NCTPP Northern 840<br />
12. Dadri Gas Northern 817<br />
13. Unchahar Northern 420<br />
14. Gandhar Western 648<br />
15. Talcher Eastern 1000<br />
16. TTPS Eastern 460<br />
Total 16795<br />
The region-wise break-up <strong>of</strong> the above capacity is given below:<br />
Northern<br />
SUMMARY<br />
Western Eastern Southern Total<br />
Thermal(MW) 4260 3360 3900 2100 13620<br />
Gas(MW) 1882 1293 0 0 3175<br />
Total 6142 4653 3900 2100 16795<br />
The Capacity Addition programme <strong>of</strong> NTPC for <strong>1<strong>99</strong>8</strong>-<strong>99</strong> is as under:-<br />
PROJECT APPROVED CAPACITY MW) BE <strong>1<strong>99</strong>8</strong>-<strong>99</strong> (MW)<br />
KAYAMKULAM 350 115<br />
The capital expenditure incurred during 1<strong>99</strong>7-98 is Rs.1504.95 crore (tentative) against<br />
the Revised Estimates 1<strong>99</strong>7-98 <strong>of</strong> Rs.1576.58 crore.<br />
Further, NTPC has generated 106291 MUs <strong>of</strong> electricity during the year 1<strong>99</strong>7-98 against<br />
the previous year generation <strong>of</strong> 97609 MUs and the coal stations <strong>of</strong> NTPC registered a<br />
PLF <strong>of</strong> 75.2%. NTPC has plans to generate <strong>99</strong>001 Mus during <strong>1<strong>99</strong>8</strong>-<strong>99</strong>.<br />
11.1.3 JOINT VENTURE PARTICIPATION BY NTPC:<br />
(a) Spectrum <strong>Power</strong> Generation Limited<br />
NTPC has co-promoted Godavari Gas <strong>Power</strong> Project (207 MW) Duel Fuel fired<br />
combined cycle power project at Kakinada in Andhra Pradesh, along with Spectrum<br />
Technologies, USA (STUSA) and Jaya Food Industries (JFI), Hyderabad to form<br />
Spectrum <strong>Power</strong> Generation Limited. NTPC is the technical consultants to the project.<br />
Three gas turbines have already been commissioned in May <strong>1<strong>99</strong>8</strong>. Owing to disputes<br />
arising out <strong>of</strong> non-compliance <strong>of</strong> the promoters agreement, NTPC has initiated legal<br />
proceedings against the co-promoters in the Delhi High Court. The judgement is awaited.<br />
79