3.3 KISHENPUR - MOGA TRANSMISSION SYSTEM<br />

The Kishenpur-Moga 800 KV Transmission system was approved by Government in<br />

May.’93. The world Bank assistance is available for this project. The Transmission<br />

system envisaged the construction <strong>of</strong> Kishenpur-Moga 2 X S/C <strong>of</strong> 800 KV line associated<br />

terminal equipments at Kishenpur and Moga. The Kishenpur-Moga (2 X S/C)<br />

transmission line along with the associated substation are expected to be commissioned<br />

in ’03/2000.<br />

3.4 KATHALGURI TRANSMISSION SYSTEM<br />

The Kathalguri Transmission System has been designed to evacuate power from<br />

Kathalguri combined cycle power project as well as from the existing power projects<br />

and new projects like Doyang, Ranganadi etc., in the North Eastern Region. All the<br />

transmission lines and associated sub station shall be completed by 03/<strong>99</strong>. The actual<br />

expenditure upto 1<strong>99</strong>6-97 is Rs.79096 lakh. The BE / RE 1<strong>99</strong>7-98 and BE <strong>1<strong>99</strong>8</strong>-<strong>99</strong> are<br />

Rs.9537 lakh/Rs.9170 lakh & Rs.4344 lakh respectively.<br />

3.5 VINDHYACHAL ADDITIONAL TRANSMISSION LINES PROJECT<br />

The Vindhyachal Additional Transmission lines project was approved in May 1989 for<br />

evacuation <strong>of</strong> power from Vindhyachal STPP Stage-I (1260 MW). The World Bank assistance<br />

<strong>of</strong> Rs.350 million is mainly available for this project. All the transmission lines and associated<br />

sub station has been completed and successfully test charged on 15.12.97. The line is presently<br />

under commercial operation.<br />

3.6 FEROZ GANDHI UNCHAHAR STAGE - II TRANSMISSION SYSTEM<br />

The Unchahar Transmission system stage - II was approved by Government in April 1<strong>99</strong>6.<br />

All packages have been awarded and supplies commenced. Foundation and Erection works<br />

are in progress. Transmission lines and associated sub station shall be completed by 01/2000<br />

matching with evacuation requirement. The actual work on this transmission line is started<br />

during the financial year 1<strong>99</strong>7-98.<br />

3.7 CHANDRAPUR HVDC BACK TO BACK PROJECT<br />

The Chandrapur HVDC Back to Back project was approved by Govt. <strong>of</strong> India in<br />

November 1<strong>99</strong>3 with an approved cost <strong>of</strong> Rs.900.28 crore. The scope <strong>of</strong> the project is<br />

as follows:-<br />

1. HVDC Back to Back station <strong>of</strong> 1000 MW(2 x 500 MW) at Chandrapur.<br />

2. 400 KV single circuit Ac Tr. line between Hyderabad and Ramagundam.<br />