3.3 KISHENPUR - MOGA TRANSMISSION SYSTEM<br />
The Kishenpur-Moga 800 KV Transmission system was approved by Government in<br />
May.’93. The world Bank assistance is available for this project. The Transmission<br />
system envisaged the construction <strong>of</strong> Kishenpur-Moga 2 X S/C <strong>of</strong> 800 KV line associated<br />
terminal equipments at Kishenpur and Moga. The Kishenpur-Moga (2 X S/C)<br />
transmission line along with the associated substation are expected to be commissioned<br />
in ’03/2000.<br />
3.4 KATHALGURI TRANSMISSION SYSTEM<br />
The Kathalguri Transmission System has been designed to evacuate power from<br />
Kathalguri combined cycle power project as well as from the existing power projects<br />
and new projects like Doyang, Ranganadi etc., in the North Eastern Region. All the<br />
transmission lines and associated sub station shall be completed by 03/<strong>99</strong>. The actual<br />
expenditure upto 1<strong>99</strong>6-97 is Rs.79096 lakh. The BE / RE 1<strong>99</strong>7-98 and BE <strong>1<strong>99</strong>8</strong>-<strong>99</strong> are<br />
Rs.9537 lakh/Rs.9170 lakh & Rs.4344 lakh respectively.<br />
3.5 VINDHYACHAL ADDITIONAL TRANSMISSION LINES PROJECT<br />
The Vindhyachal Additional Transmission lines project was approved in May 1989 for<br />
evacuation <strong>of</strong> power from Vindhyachal STPP Stage-I (1260 MW). The World Bank assistance<br />
<strong>of</strong> Rs.350 million is mainly available for this project. All the transmission lines and associated<br />
sub station has been completed and successfully test charged on 15.12.97. The line is presently<br />
under commercial operation.<br />
3.6 FEROZ GANDHI UNCHAHAR STAGE - II TRANSMISSION SYSTEM<br />
The Unchahar Transmission system stage - II was approved by Government in April 1<strong>99</strong>6.<br />
All packages have been awarded and supplies commenced. Foundation and Erection works<br />
are in progress. Transmission lines and associated sub station shall be completed by 01/2000<br />
matching with evacuation requirement. The actual work on this transmission line is started<br />
during the financial year 1<strong>99</strong>7-98.<br />
3.7 CHANDRAPUR HVDC BACK TO BACK PROJECT<br />
The Chandrapur HVDC Back to Back project was approved by Govt. <strong>of</strong> India in<br />
November 1<strong>99</strong>3 with an approved cost <strong>of</strong> Rs.900.28 crore. The scope <strong>of</strong> the project is<br />
as follows:-<br />
1. HVDC Back to Back station <strong>of</strong> 1000 MW(2 x 500 MW) at Chandrapur.<br />
2. 400 KV single circuit Ac Tr. line between Hyderabad and Ramagundam.<br />
118