Rs. 100 lakh. The actual expenditure during the year 1<strong>99</strong>7-98 was Rs. 183.72 lakh. The<br />

Simulator has now been commissioned and training has commenced w.e.f 23.3.98.<br />

Fine Tuning and the documentation shall be completed during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong> and<br />

the simulator will become fully operational for training. The actual expenditure upto<br />

31.3.98 is Rs.1634.90 lakh.<br />

ii) Installation <strong>of</strong> 500 MW Simulator at Faridabad:<br />

The scheme was sanctioned on 13.8.90 at an estimated cost <strong>of</strong> RS.1840.12 lakh. The<br />

works for manufacturing/installation <strong>of</strong> 500 MW Simulator were awarded to M/s. ECIL,<br />

Hyderabad on 17.2.94. The actual expenditure upto 31.3.98 is Rs.1780.82 lakh. An<br />

amount <strong>of</strong> Rs. 123.76 lakh was provided where as the actual expenditure during the<br />

year 1<strong>99</strong>7-98 was Rs.82.57 lakh. The amount provided in the 1<strong>99</strong>7-98 budget could<br />

not be utilised, as the various mile stones fixed could not be achieved despite the close<br />

monitoring and interaction between NPTI and ECIL. The scheme will be completed<br />

during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong> i.e. the balance works like Acceptance testing, Fine tuning and<br />

Documentation <strong>of</strong> the complete system which are at advanced stage <strong>of</strong> completion at<br />

present. The expenditure during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong> would be <strong>of</strong> the order <strong>of</strong> Rs.53.06<br />

lakh.<br />

iii) Setting up <strong>of</strong> N.P.T.I.<br />

The scheme for setting up <strong>of</strong> NPTI together with an Institute for Advanced Learning &<br />

Management Studies (INALMAS) was sanctioned on 26.6.91 at an estimated cost <strong>of</strong><br />

Rs.1273 lakh. The entire civil works are being executed through CPWD. All the civil<br />

works <strong>of</strong> staff quarters, 50 Room Executive Hostel, Institute building have been<br />

completed. 90% furnishing works <strong>of</strong> Executive Hostel and Institute Building have been<br />

completed. Sports Complex with recreation facilities is under construction. A sum <strong>of</strong><br />

Rs.491.73 lakhs was provided in the BE 1<strong>99</strong>7-98 which was revised to Rs.285.50 lakh<br />

because the construction <strong>of</strong> Transit Accommodation and Garages could not be taken<br />

up due to the Hon’ble Supreme Court Ruling setting out fresh guidelines for sanctioning<br />

building plans for new construction in areas within 5 kms. radius <strong>of</strong> Badkal Lake. The<br />

actual expenditure during the year 1<strong>99</strong>7-98 was Rs.244.72 lakh. A sum <strong>of</strong> Rs.201.93<br />

lakh would be required during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong> as it is expected that works like<br />

construction <strong>of</strong> Sports complex, Transit accommodation, Garages etc. will be completed<br />

during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong>. The actual expenditure upto 31.3.98 is Rs.1051.11 lakh.<br />