additional or improved environmental safeguards, if any, based on data and information<br />

now available.<br />

The Committee submitted its report to Governement <strong>of</strong> India on 11.11.1<strong>99</strong>7, Government<br />

<strong>of</strong> India constituted an Inter Ministerial Committee headed by, Secretary (Rural<br />

Development) and included representative <strong>of</strong> U.P.Government with a view to finalise<br />

the Government’s view on the recommendations <strong>of</strong> the Hanumatha Rao Committee.<br />

The report <strong>of</strong> the Inter-Ministerial Committee was submitted to the Government during March,<br />

<strong>1<strong>99</strong>8</strong>. Further action for the implementation <strong>of</strong> the recommendations would be taken once<br />

they are approved.<br />

5.5 TARGETS<br />

The following major activities have been planned during the year <strong>1<strong>99</strong>8</strong>-<strong>99</strong>:-<br />

1. Completion <strong>of</strong> Excavation/core stripping in the Main Dam.<br />

2 Completion <strong>of</strong> excavation <strong>of</strong> 4 Nos. Control Gate Shaft in Intake area.<br />

3. Engagement <strong>of</strong> Agency for Main Civil Works <strong>of</strong> Spillway.<br />

4. Completion <strong>of</strong> crane beam concreting in <strong>Power</strong> House.<br />

5. Completion <strong>of</strong> excavation in Butterfly Valve Chamber.<br />

6. Completion <strong>of</strong> excavation in Penstock Assembly Chamber Horizontal Penstock.<br />

7. Completion <strong>of</strong> excavation in Machine Hall/Transformer Hall.<br />

8. Start <strong>of</strong> concreting in Machine Hall <strong>of</strong> <strong>Power</strong> House.<br />

9. Completion <strong>of</strong> excavation <strong>of</strong> 2 No. Tail Race Tunnels.<br />

5.6 COMMISIONING SCHEDULE<br />

Tehri Hydro <strong>Power</strong> Project 1000 MW (4x250 MW) is likely to be commissioned by<br />

March, 2002.<br />

5.7 EXPENDITURE ON THE PROJECT<br />

The total expenditure incurred so far on the project till March, <strong>1<strong>99</strong>8</strong> was Rs. 1650.86<br />

crore (provisional) (including Rs. 8.41 crore spent on associated Transmission System<br />

being executed by PGCIL).<br />

6. NATHPA JHAKRI POWER CORPORATION (NJPC):<br />

NATHPA JHAKRI HYDRO ELECTRIC POWER PROJECT (6X250 MW):<br />

NJPC is presently executing its firs mega project, namely, Nathpa Jhakri Hydro Electric<br />

<strong>Power</strong> Project (NJHPP) in Himachal Pradesh with the resources funded by World Bank.<br />

The details <strong>of</strong> the project as under:<br />

124