The project is proposed to be executed in a period <strong>of</strong> 5 years from the date <strong>of</strong> start <strong>of</strong><br />

active construction.<br />

For construction, 78.8 ha. Of Govt. land and 23 ha. <strong>of</strong> private land has already been<br />

acquired. The project has completed the construction <strong>of</strong> approach roads, temp. <strong>of</strong>fice<br />

buildings, store sheds etc.<br />

1.7 The project-wise details <strong>of</strong> estimated cost, actual expenditure incurred upto 3/98, budget<br />

provision made in BE/RE 1<strong>99</strong>7-98 and BE <strong>1<strong>99</strong>8</strong>-<strong>99</strong> regard to capital construction<br />

projects <strong>of</strong> NHPC are provided in Annexure-X.<br />

2. NATIONAL THERMAL POWER CORPORATION (NTPC):<br />

2.1 Vindhyachal STPP Stage-II (2x500 MW)<br />

This is the second stage <strong>of</strong> the project. The project has been approved by the Govt. <strong>of</strong><br />

India in February 1<strong>99</strong>5. The approved cost <strong>of</strong> the Project is Rs.2753.38 crore and shall<br />

be part financed from IBRD time slice loan. Main plant has been awarded to M/s BHEL<br />

in 3/95 and other main packages have also since been awarded. Boiler erection is in<br />

progress for both the units and is as per schedule. The civil and structural work in<br />

respect <strong>of</strong> main power-house, chimney, cooling towers etc. and erection <strong>of</strong> ESP are<br />

progressing as per schedule. The project is expected to be commissioned as per schedule,<br />

i.e., Unit I in Feb. 2000 and Unit II in Feb. 2001.<br />

2.2 Feroze Gandhi Unchahar TPP (2x210 MW) Stage II<br />

The second stage <strong>of</strong> the project consisting <strong>of</strong> two units <strong>of</strong> 210 MW each to be constructed<br />

at a cost <strong>of</strong> Rs.1279.51 crore has been approved by the Govt. <strong>of</strong> India in April 1<strong>99</strong>5 and<br />

shall be part financed from ADB. Boiler erection work is in progress. Civil work <strong>of</strong><br />

Cooling Tower, Coal Handling Plant, CW system etc. are progressing as per schedule.<br />

The two units are expected to be commissioned in Jan. 2000 and July 2000 respectively.<br />

2.3 Kayamkulam CCP (2x115 + 1x120 MW)<br />

The project was approved by Govt. <strong>of</strong> India on 18.09.96 at an estimated cost <strong>of</strong><br />

Rs.1310.58 crore and the main plant has been awarded to M/s BHEL on 18.09.96<br />

itself. The project is to be part financed from the time slice loan from IBRD.<br />

The foundation <strong>of</strong> Gas Turbine #1 has been completed and for GT#2, the work has<br />

commenced. Dredging, levelling and dynamic compaction has been successfully<br />

completed in main plant, <strong>of</strong>f-site and fuel-handling areas. All other works under various<br />

packages are progressing as per schedule. The various units <strong>of</strong> the projects are scheduled<br />

to be commissioned as under:<br />