PERFORMANCE BUDGET 1998-99 - Ministry of Power
PERFORMANCE BUDGET 1998-99 - Ministry of Power
PERFORMANCE BUDGET 1998-99 - Ministry of Power
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
energy generation <strong>of</strong> 1928 million unit. The project was taken up for execution under<br />
bilateral agreement signed between N.H.P.C. and French Consortium in September,<br />
1989 for completion <strong>of</strong> the project in 57 months. Due to increased militant activities in<br />
the project area, M/s DSB, the civil contractor <strong>of</strong> the French Consortium suspended<br />
works at site in August’92.<br />
The contract with M/s. DSB had been terminated following signing <strong>of</strong> Recession<br />
Agreement between DSB and NHPC alongwith an overall amended contract between<br />
French consortium and NHPC in June 1<strong>99</strong>5. The contract for balance civil work has<br />
been awarded to M/s JSA (JV) an Indo-Norwegian joint venture on 9.4.97. However to<br />
utilise intervening period, execution <strong>of</strong> HRT by Drilling and Blasting method from<br />
downstream side was resumed departmentally in August’95 and from upstream side<br />
with TBM in Nov.,95. After award <strong>of</strong> work to new contractor departmental works were<br />
handed over to the JV who have started the work since April 97. Upto March,’98 in<br />
Dam area, 100% excavation, 36% concreting, and 70% Intake tower concreting have<br />
been completed. In HRT 30% excavation from upstream side by TBM & 61% excavation<br />
from downstream side by drilling & blasting method have been completed. Excavation<br />
<strong>of</strong> power house cavern, transformer cavern and switchyard have been completed. Supply<br />
<strong>of</strong> 93% <strong>of</strong> hydro-mechanical and electric-mechanical equipment has been completed.<br />
The project was accorded Government sanction for an amount <strong>of</strong> Rs.1262.97 crore<br />
(October, 1988 price level). The revised sanctioned cost <strong>of</strong> the project is now Rs.3559.77<br />
crore (at November, 1<strong>99</strong>6 price level). The increase in the estimated cost is mainly on<br />
account <strong>of</strong> price escalation, cost <strong>of</strong> balance civil works, exchange rate variation and<br />
rise in financing charges etc. The actual expenditure on the project upto March,’98 is<br />
Rs.1866.56 crore. The project is scheduled for completion by March 2001.<br />
1.3 Rangit H.E. Project (3 x 20 M.W.)<br />
Rangit project under execution <strong>of</strong> N.H.P.C. is a run <strong>of</strong> the river scheme to utilise power<br />
potential <strong>of</strong> the river Rangit, a tributary <strong>of</strong> river Teesta in Sikkim. The estimated annual<br />
generation <strong>of</strong> energy from this project <strong>of</strong> 60 M.W. installed capacity will be 343 M.U.<br />
The project was approved in September, 1<strong>99</strong>0 with an estimated cost <strong>of</strong> Rs.163.49<br />
crores (excluding transmission) which is likely to go up to Rs.364.41 crores (January,<br />
<strong>1<strong>99</strong>8</strong> price level - excluding transmission). The increase in the estimated cost is mainly<br />
due to price escalation, variation in scope and IDC.<br />
Progress <strong>of</strong> all major components <strong>of</strong> the project is in full swing as the diversion tunnel<br />
has been completed. The Excavation <strong>of</strong> main Dam has been completed (68,000 cum.).<br />
4500 cum. <strong>of</strong> concrete as targetted has been placed in the dam during March,’98<br />
and cumulative progress <strong>of</strong> 23,500 (26%) has been achieved. In Head Race Tunnel,<br />
112