Expenditure during 4/97 to 3/98 : Rs.2.60 Crore (Provisional)<br />

Cumulative Expenditure till 3/98 : Rs.337.31 crore (Provisional)<br />

5. TEHRI HYDRO DEVELOPMENT CORPORATION:<br />

5.1 SCOPE & OBJECTIVES<br />

Tehri Hydro Complex (2400 MW) was transferred to THDC by Government <strong>of</strong> U.P. in<br />

June, 1989. On 15.3.94, Government <strong>of</strong> India accorded investment approval for<br />

execution <strong>of</strong> Tehri Dam & HPP Stage-I (4x250 MW) alongwith the essential and<br />

committed works <strong>of</strong> Tehri Pump Storage Plant & Koteshwar Dam project respectively<br />

at an estimated cost <strong>of</strong> Rs.2963.66 crore, (at March, 1<strong>99</strong>3 price level). The share <strong>of</strong> cost<br />

<strong>of</strong> the project (<strong>Power</strong> Component) is in the 75:25 by Government <strong>of</strong> India and Govt. <strong>of</strong><br />

U.P. respectively. The irrigation sector is to be funded entirely by the Government <strong>of</strong><br />

UP.<br />

5.2 Project benefits:<br />

The project is a multipurpose project serving the purpose <strong>of</strong> peaking power generation,<br />

irrigation and drinking water supplies. The benefits from the project are as under:<br />

- Addition to the installed generating capacity in the<br />

Northern Region : 1000 MW<br />

- Annual energy (mostly to meet the peaking requirement <strong>of</strong> the<br />

region) : 3568 MU<br />

- Irrigation (additional) : 2.7 lakh ha.<br />

- Stabilisation <strong>of</strong> Irrigation (besides above) : 6.00 lakh ha.<br />

- Drinking water for Delhi which will meet the requirement <strong>of</strong><br />

about 40 lakh people(162 mi.gallons) : 300 cusec. /day<br />

- In addition, supply <strong>of</strong> drinking water for towns and Villages <strong>of</strong><br />

UP (108 million gallons) : 200 cusec. /day<br />

- Integrated development <strong>of</strong> Garhwal region including construction <strong>of</strong> a new hill station<br />

town with provision <strong>of</strong> all civic facilities; improved communication, education, health,<br />

tourism, development <strong>of</strong> horticulture, fisheries and afforestation <strong>of</strong> the region.<br />

5.3 ACHIEVEMENT AGAINST TARGETS<br />

A) MAIN DAM: The work <strong>of</strong> Main Dam was awarded in January, 1<strong>99</strong>7. The construction<br />

works at site were progressing satisfactorily till Sept.,’97, thereafter there had been hindrances<br />

to the work due to local resistance and Government <strong>of</strong> India’s<br />