A) External Loan :-<br />

83<br />

Rs. in crores<br />

i) Chameral-I - EDC 356.29<br />

ii) Uri - Chartered West L.B.Ltd. 167.23<br />

- Skandinaviska 655.53<br />

- Nordic Investment Bank 184.04<br />

1006.80<br />

iii) Dulhasti - C.C.D.F. 395.98<br />

Total External Loan (A) 1759.07<br />

B) Bonds & others 2667.00<br />

C) Govt. Loan (Net after repayment) 618.24<br />

D) Interest Accrued and due on GOI loan 179.03<br />

Total Loans (A to D) 5223.34<br />

11.2.3 COMPLETED HYDRO-POWER PROJECTS:<br />

The Corporation has so far completed construction <strong>of</strong> eight hydro-electric projects and<br />

added 2133 MW <strong>of</strong> generating capacity till the end <strong>of</strong> March, ‘98, the details <strong>of</strong> which<br />

are as under:-<br />

PROJECTS STATE INSTALLED YEAR OF<br />

CAPACITY (MW) COMPLETION<br />

1) BAIRA SIUL H.P. 198 1982<br />

2) LOKTAK MANIPUR 105 1983<br />

3) SALAL - I J&K 345 1987<br />

4) TANAKPUR U.P. 120 1<strong>99</strong>2<br />

5) CHAMERA - I H.P. 540 1<strong>99</strong>4<br />

6) SALAL - II J&K 345 1<strong>99</strong>6<br />

7) URI J&K 480 1<strong>99</strong>7<br />

8) DEVIGHAT NEPAL 14 1984<br />

(On Agency basis)<br />

First seven <strong>of</strong> the above projects are in the ownership <strong>of</strong> the Corporation and are<br />

generating power. However, Devighat project was done on Agency basis and handed over<br />

to Govt. <strong>of</strong> Nepal after completion.