A) External Loan :-<br />
83<br />
Rs. in crores<br />
i) Chameral-I - EDC 356.29<br />
ii) Uri - Chartered West L.B.Ltd. 167.23<br />
- Skandinaviska 655.53<br />
- Nordic Investment Bank 184.04<br />
1006.80<br />
iii) Dulhasti - C.C.D.F. 395.98<br />
Total External Loan (A) 1759.07<br />
B) Bonds & others 2667.00<br />
C) Govt. Loan (Net after repayment) 618.24<br />
D) Interest Accrued and due on GOI loan 179.03<br />
Total Loans (A to D) 5223.34<br />
11.2.3 COMPLETED HYDRO-POWER PROJECTS:<br />
The Corporation has so far completed construction <strong>of</strong> eight hydro-electric projects and<br />
added 2133 MW <strong>of</strong> generating capacity till the end <strong>of</strong> March, ‘98, the details <strong>of</strong> which<br />
are as under:-<br />
PROJECTS STATE INSTALLED YEAR OF<br />
CAPACITY (MW) COMPLETION<br />
1) BAIRA SIUL H.P. 198 1982<br />
2) LOKTAK MANIPUR 105 1983<br />
3) SALAL - I J&K 345 1987<br />
4) TANAKPUR U.P. 120 1<strong>99</strong>2<br />
5) CHAMERA - I H.P. 540 1<strong>99</strong>4<br />
6) SALAL - II J&K 345 1<strong>99</strong>6<br />
7) URI J&K 480 1<strong>99</strong>7<br />
8) DEVIGHAT NEPAL 14 1984<br />
(On Agency basis)<br />
First seven <strong>of</strong> the above projects are in the ownership <strong>of</strong> the Corporation and are<br />
generating power. However, Devighat project was done on Agency basis and handed over<br />
to Govt. <strong>of</strong> Nepal after completion.