05.01.2013 Views

Ontario Power Generation's Response to the Joint Review

Ontario Power Generation's Response to the Joint Review

Ontario Power Generation's Response to the Joint Review

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Attachment 1 <strong>to</strong> OPG letter, Albert Sweetnam <strong>to</strong> Dr. Stella Swanson, “Deep Geologic Reposi<strong>to</strong>ry Project for Low and Intermediate Level Waste – Submission of<br />

<strong>Response</strong>s <strong>to</strong> <strong>the</strong> Final Sub-set of Package #4 Information Requests”, CD#: 00216-CORR-00531-00143.<br />

IR# EIS Guidelines<br />

Section<br />

Information Request and <strong>Response</strong><br />

on <strong>the</strong> conservative assumption of no grouting, it is estimated that groundwater inflow from <strong>the</strong>se formations will be<br />

0.38 L/s. However, during shaft sinking it is expected that <strong>the</strong>se formations will be grouted, as required, <strong>to</strong> primarily<br />

reduce groundwater inflow later during DGR operations (see below).<br />

Once shaft sinking is complete and both shafts are fully lined with concrete, groundwater inflow through concrete liners<br />

is estimated <strong>to</strong> be 0.45 L/s (GOLDER 2012). This estimate is based on <strong>the</strong> assumption that <strong>the</strong> majority of inflow<br />

occurs from Salina A1 and Guelph Formations through a “leaky liner” and <strong>the</strong>se two formations are ungrouted (see<br />

responses <strong>to</strong> IR-LPSC-01-17 (OPG 2012a) and Undertaking TIS 11 (OPG 2012b)). However, since it is expected that<br />

<strong>the</strong>se formations will be grouted during shaft sinking, <strong>the</strong> groundwater inflow will be less than 0.45 L/s.<br />

During lateral development at <strong>the</strong> reposi<strong>to</strong>ry level, <strong>the</strong> usage of process water for equipment, construction and dust<br />

mitigation is assumed <strong>to</strong> be about 20 L/s (average). This estimate is very conservative <strong>to</strong> allow for a wide variety of<br />

equipment selection and water demand criteria. The estimate has been derived using high water demand equipment<br />

(e.g., high efficiency multi-boom drilling jumbos), high utilization estimates for operating hours per day, continuous<br />

water suppression during operating hours and an allowance for continuous civil construction activities (e.g., floor<br />

concrete). As well, this estimate does not take in<strong>to</strong> consideration options for recirculation of process water.<br />

The expected inflow rates during normal operations are described in <strong>the</strong> response <strong>to</strong> Undertaking TIS 11 (OPG 2012b).<br />

During normal operations, <strong>the</strong> majority of groundwater inflow will be through both shaft concrete liners and as described<br />

above is conservatively estimated <strong>to</strong> be 0.45 L/s. Due <strong>to</strong> <strong>the</strong> very low permeability of <strong>the</strong> Cobourg Formation Lower<br />

Member, groundwater inflow at <strong>the</strong> reposi<strong>to</strong>ry level is expected <strong>to</strong> be negligible (0.006 L/s). This rate of groundwater<br />

inflow would likely be less than <strong>the</strong> rate at which <strong>the</strong> water would evaporate and thus would not flow <strong>to</strong> <strong>the</strong> underground<br />

dewatering system. A small allowance (0.06 L/s) has been made in <strong>the</strong> discharge water estimate <strong>to</strong> reflect potential<br />

condensation in <strong>the</strong> ventilation shaft during summer conditions.<br />

The underground dewatering system used for operations will be sized <strong>to</strong> handle both <strong>the</strong> aforementioned normal inflow<br />

plus additional groundwater inflow that might occur during a postulated abnormal operations event. In <strong>the</strong> Preliminary<br />

Safety Report (OPG 2011, Section 6.3.10.4) it was assumed that an abnormal ’in-rush scenario’ would lead <strong>to</strong> an<br />

additional groundwater inflow of 15 L/s. Fur<strong>the</strong>r assessment of potential additional inflow due <strong>to</strong> shaft liner impairments<br />

has been completed (GOLDER 2011, enclosed). This assessment shows that a 1:2500 year seismic event, which is<br />

consistent with <strong>the</strong> National Building Code of Canada (2010 edition) requirements, could lead <strong>to</strong> cracking of shaft liners<br />

and an additional 0.1 L/s inflow. A fur<strong>the</strong>r analysis was conducted for a beyond-design-basis 1:100,000 year seismic<br />

event which resulted in a potential inflow of 3.4 L/s.<br />

References:<br />

GOLDER. 2011. Potential Inflows through Cracked Hydrostatic Concrete Shaft Liner. Golder Associates Ltd.<br />

Technical Memorandum 1011170042-TM-G2100-0001-01 R01. (enclosed)<br />

GOLDER. 2012. Underground Services (WP2-10) Underground Reposi<strong>to</strong>ry Dewatering – Preliminary Estimate of<br />

Groundwater Inflow under Normal Operating Conditions. Golder Associates Ltd. Technical Memorandum No.<br />

Page 53 of 69

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!