13.01.2013 Views

Dames & Moore, 1999 - USDA Forest Service

Dames & Moore, 1999 - USDA Forest Service

Dames & Moore, 1999 - USDA Forest Service

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Section I-I' and shows the six tunnels which accessed the ore body and stopes. The levels of the mine were<br />

numbered based on the approximate elevation below an exposure of the ore body outcrop shown on Figure<br />

4.1-5b; in other words, the exposure of the ore body is the hypothetical "0" level, with the 300-level being<br />

300 feet lower, the 550-level being 550 feet lower, and so on to the 2500-level. The northing and easting<br />

grid system noted on the maps were established utilizing the general strike of the ore body as the northing<br />

line.<br />

The six levels of the mine with portals to the surface, as well as the most laterally extensive lower level<br />

(2325), depicted on Figures 4.1-5c and 4.1-5d, were digitized utilizing the underground mine maps<br />

provided. Figure 4.1-5b shows all seven levels with the associated stopes and mine workings superimposed.<br />

However, Figures 4.1-6 through 4.1 - 13 show the extent of each individual mine level (300, 550, 700, 800,<br />

1000, 1 100, 1500, and 2325, respectively.<br />

The map utilized to generate Figure 4.1-5c displayed the dates of mining for each of the stopes. The upper<br />

workings (300-, 550-, and 700-levels) (Figures 4.1-6 through 4.1-8) were apparently developed during the<br />

early periods of the exploratory efforts. The lower workings (800-, 1000-, and I 100-levels) (Figures 4.1-9<br />

through 4.1- 1 1) were developed during the period from approximately 1920 until 1937, and included several<br />

miles of tunnels. This corresponds to the relatively larger sizes of mine rock piles associated with the lower<br />

workings. All of the portals, except for the 300 level, were timbered.<br />

When Howe Sound purchased the mine, they increased access to the underground mine workings by<br />

installing a primary tunnel at the 1500 level. Referring to Figures 4.1-5b and 4.1-12, the opening to this<br />

tunnel was constructed near and to the west of the uppermost level of the mill building. The tunnel was<br />

initially installed by timber supporting the approximately 60 to 70 feet of glacial soil encountered at the<br />

portal. The remainder of the tunnel was drilled and blasted with limited rock bolt support to intersect the ore<br />

body approximately 2,500 feet to the southwest. A track was placed on the floor of the tunnel to allow the<br />

use of ore cars which transported the non-mineralized rock to the west and east waste rock piles. The tunnel<br />

was driven at an incline of approximately one-half percent to take advantage of gravity when the ore cars<br />

were filled in the mine (McWilliarns, 1958).<br />

Once the ore body was intersected, the tunnel turned and continued to the northwest approximately another<br />

2,500 feet before daylighting out to the west at the 1500-level ventilator portal (Figure 4.1-12). The maps<br />

indicate that the last approximately 300 feet of the tunnel was timbered through glacial soil. This tunnel was<br />

utilized to provide ventilation throughout the mine. Air was piped in through the 1500-level main portal and<br />

then exhausted through the 1500-level ventilator portal; an 8-foot-diameter fan was originally installed in<br />

the opening (Edrnond, 1972). Based on a civil survey completed as part of the RI, the ventilator portal was<br />

found to be approximately 20 feet higher than the 1500-level main portal. This indicates that the one-half<br />

percent grade continues for the entire length of the tunnel from the 1500-level main portal.<br />

The majority of the mine tunnels at the different levels were generally constructed outside the ore body,<br />

within the surrounding rock which, based on the mine maps, had relatively low concentrations of economic<br />

minerals. The rock removed during the construction of the tunnels, after the 1500-level main tunnel was<br />

completed, was generally placed in two piles developed to the west and east of the mill. The tunnels within<br />

rock were constructed without timber support; however, rock bolts were utilized where necessary. The<br />

1500-level was utilized to explore the lateral extent of.the ore body; the maps reviewed indicate that the<br />

G:\WPDATA\OOJ\REPORTSWOLDEN-2WW.DOC<br />

17693-005-019Uuly 19. <strong>1999</strong>:4:51 PM:DRAFT FINAL RI REPORT

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!