• Improved communication among donors, public, and private<br />

sectors on ODA<br />

• Improved and faster ICT<br />

B. Cost estimates and financing plan<br />

The total cost of <strong>the</strong> project is estimated at US$ 1.2 million, of<br />

which 0.80 is <strong>the</strong> <strong>for</strong>eign exchange and 0.40 is <strong>the</strong> local cost. The cost<br />

estimate includes contingencies, but excludes tax, duties; and physical, and<br />

price contingency charges during <strong>the</strong> project implementation. It is expected<br />

that ADB, United Nations agencies, and <strong>the</strong> private sector will provide a<br />

grant of US$ 1.2 million and <strong>the</strong> <strong>Government</strong> would contribute <strong>for</strong> <strong>the</strong><br />

staffing, duties, and taxes.<br />

COST ESTIMATES<br />

(US$ million)<br />

Lao People’s Democratic Republic<br />

Component Foreign Local Total<br />

Base cost<br />

In<strong>for</strong>mation centre office equipment 0.50 0.15 0.65<br />

Consultant service 0.25 0.05 0.30<br />

Project administration 0.00 0.10 0.10<br />

Contingencies 0.05 0.10 0.15<br />

Total 0.80 0.40 1.20<br />

C. Implementation arrangements<br />

The Division of International Financial Institution, Ministry of Foreign<br />

Affairs will be <strong>the</strong> implementing agency.<br />

D. Implementation schedule<br />

The project will be implemented over a period of three years<br />

starting in June 2005 and ending in May 2008.<br />

E. Technical and economic justifications<br />

The project will directly benefit <strong>the</strong> public and private sectors, and<br />

donors by linking <strong>the</strong>se stakeholders directly to a computerized in<strong>for</strong>mation<br />

sharing system. This project is <strong>the</strong> initial stage of setting up an egovernment<br />

network <strong>for</strong> ODA coordination.<br />

Sustainability depends on operation and maintenance. However, after<br />

completion of <strong>the</strong> project, sustainability will rely on staff capacity, and <strong>the</strong><br />

ability to provide better services to <strong>the</strong> citizens.<br />