136<br />
Mongolia<br />
B. Cost estimates and financing plan<br />
COST ESTIMATES<br />
(US$ million)<br />
Project name Period <strong>Government</strong> Donors Total<br />
Project 1: Infrastructure project 5 year 7.1 27.9 35.0<br />
1 st stage – Centres and backbone 1 year 2.6 12.5 15.1<br />
1. Consultants 1.5<br />
a. International 0.0 1.0 1.0<br />
b. Domestic 0.5 0.0 0.5<br />
2. Equipment and software 8.0<br />
a. Equipment 1.0 7.0 6.0<br />
b. Software 0.0 2.0 2.0<br />
3. Building and furniture 2.3<br />
a. Building 0.5 1.5 2.0<br />
b. Furniture 0.0 0.3 0.3<br />
4. Training seminars conferences 0.1 0.2 0.3<br />
5. Research development and<br />
surveys<br />
0.2 0.5 0.7<br />
6. Miscellaneous administration<br />
and support costs<br />
0.1 0.2 0.3<br />
7. Contingencies 0.2 1.8 2.0<br />
2 nd stage – 21 centres and<br />
connections<br />
2 years 2.0 8.3 10.3<br />
1. Consultants 1.0<br />
a. International 0.0 0.5 0.5<br />
b. Domestic 0.5 0.0 0.5<br />
2. Equipment and software 4.0<br />
a. Equipment 0.5 3.5 4.0<br />
b. Software 0.0 0.0 0.0<br />
3. Building and furniture 2.5<br />
a. Building 0.5 1.5 2.0<br />
b. Furniture 0.0 0.5 0.5<br />
4. Training seminars conferences 0.1 0.4 0.5<br />
5. Research development and<br />
surveys<br />
0.1 0.2 0.3<br />
6. Miscellaneous administration<br />
and support costs<br />
0.2 0.5 0.7<br />
7. Contingencies 0.1 1.2 1.3<br />
3 rd stage – 330 centres and<br />
connections<br />
2 years 2.5 7.1 9.6<br />
1. Consultants 0.8<br />
a. International 0.0 0.3 0.3<br />
b. Domestic 0.5 0.0 0.5<br />
2. Equipment and software 3.0<br />
a. Equipment 0.5 2.5 3.0<br />
b. Software 0.0 0.0 0.0