<strong>Renewal</strong> Capital Expenditure<br />
TNM-GR-809-0929<br />
Issue 1.0, January 2009<br />
AER’s consultant – Nuttall Consulting – has included analysis of fleet age profiles in reaching its<br />
conclusions, further information is included regarding the age profile of the circuit breakers and<br />
other related plant in need of replacement.<br />
1.2 TRANSEND REVENUE PROPOSAL AND NUTTALL CONSULTING REVIEW<br />
<strong>Transend</strong>’s revenue proposal for the forthcoming regulatory control period included the<br />
commencement of 13 110 kV substation redevelopment projects, of which seven will be completed<br />
in the forthcoming regulatory control period. Nuttall Consulting, in its review of the asset renewal<br />
projects that were included in <strong>Transend</strong>’s revenue proposal, selected nine of the 13 110 kV<br />
substation redevelopment projects to review in detail. Of these projects, six contained Reyrolle<br />
110 kV circuit breaker replacements. A project to redevelop the entire Arthurs Lake Substation that<br />
contains one Reyrolle 110 kV circuit breaker was also selected for review.<br />
Nuttall Consulting identified linkages between the 110 kV substation redevelopment program and<br />
the Sprecher & Schuh and Reyrolle 110 kV circuit breaker replacement programs and considered<br />
that the planned circuit breaker replacements could be the trigger for much larger substation<br />
redevelopment projects.<br />
Nuttall Consulting concluded that only 60 per cent of the 110 kV substation redevelopment projects<br />
associated with the Reyrolle circuit breaker program would be required in the forthcoming<br />
regulatory control period. The substation redevelopment projects reviewed by Nuttall Consulting<br />
that include the replacement of Reyrolle 110 kV circuit breakers are presented in Table 1.<br />
Table 1 – Replacement Reyrolle 110 kV circuit breakers<br />
Project<br />
identification<br />
Project description<br />
Page 8 of 28 © <strong>Transend</strong> Networks Pty Ltd<br />
UNCONTROLLED WHEN PRINTED<br />
Estimated cost<br />
($m 2008–09)<br />
Commissioning<br />
year<br />
ND0910 Arthurs Lake Substation redevelopment 4.1 2014 1<br />
ND0908 Burnie Substation 110 kV redevelopment 8.1 2014<br />
ND0733 Creek Road Substation 110 kV redevelopment 33.1 2014<br />
ND0968 Knights Road Substation 110 kV<br />
redevelopment<br />
ND0949 Meadowbank Substation 110 kV<br />
redevelopment<br />
6.6 2015 1<br />
4.6 2015 1<br />
ND0953 Palmerston Substation 110 kV redevelopment 13.7 2014<br />
ND0709 Tungatinah Substation 110 kV redevelopment 19.5 2015 1<br />
Note 1: Commissioning dates of 2013 for project ND0910 and 2014 for ND0968, ND0949 and ND0709 were incorrectly<br />
identified for these projects on page 105 of Nuttall Consulting’s report<br />
The only other projects in <strong>Transend</strong>’s revenue proposal that included the replacement of Reyrolle<br />
110 kV circuit breakers are the Rosebery Substation HV redevelopment project (one unit) and<br />
Temco Substation 110 kV redevelopment (three units). These projects are planned to be<br />
commissioned in 2015 and 2016 respectively and were not selected for review by Nuttall<br />
Consulting. It is noted that the AER has also removed 50 per cent of the funding for the Temco<br />
Substation 110 kV redevelopment project. <strong>Transend</strong> considers that the <strong>capital</strong> <strong>expenditure</strong> for this<br />
project should be reinstated for the reasons outlined in this document.<br />
1.3 REVISED REVENUE PROPOSAL<br />
The purpose of this section is to provide further information about the 110 kV substation<br />
redevelopment projects that include the replacement of Reyrolle 110 kV circuit breakers. These<br />
projects are included in <strong>Transend</strong>’s revised revenue proposal.