24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

1 BACKGROUND<br />

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

Farrell Substation was established in 1982 to provide a connection point for the Pieman River power development and is<br />

a critical node in the Tasmanian transmission network. It connects up to 618 MW of generation to the Tasmanian power<br />

system and, in turn, the national electricity grid via Basslink. Under certain generation scenarios, Farrell Substation can<br />

transmit up to one third of Tasmania’s generation requirement. In addition, the substation is critical to providing a secure<br />

and reliable electricity supply to customers located on the west coast of Tasmania. The load supplied from Farrell<br />

Substation is predominantly for mining and minerals processing and in 2007 the maximum demand was approximately<br />

70 MW.<br />

Farrell Substation is located on Tasmania’s remote west coast and is frequently exposed to inclement weather conditions.<br />

On a number of occasions each year, the substation can not be accessed by road because of snow and ice. In addition, the<br />

substation is approximately two hours drive from the nearest fault response centre. Therefore, adequate remote control<br />

and monitoring facilities are essential to ensuring the security, reliability and availability of the transmission network.<br />

The two existing bus bar protection schemes (one each on the 220 kV and 110 kV) were commissioned in 1983 as part of<br />

the original substation development. The protection relays are now 25 years old and are well beyond their nominal<br />

service life of 15 years. They are Brown Boveri type INX2 static low impedance schemes and are the only bus bar<br />

protection schemes of this type in <strong>Transend</strong>’s transmission network.<br />

2 PROJECT OVERVIEW<br />

This project comprises the replacement of the 220 kV and 110 kV bus bar protection schemes at Farrell Substation. The<br />

bus bar protection schemes will be replaced with new duplicate schemes on both the 110 kV and 220 kV bus bars.<br />

The new bus bar protection schemes will be installed in the existing relay room at Farrell Substation. New multi-core<br />

cabling will be required within the relay room to connect the new panels to Current Transformer, trip, control, AC/DC<br />

supplies, disconnector imaging and SCADA circuits. The project also includes the installation of a small quantity of<br />

cabling from the switchyard to the control building, but it does not include provision for new multi-core cabling between<br />

assets located in the switchyard. Preliminary investigations indicate that there is sufficient spare capacity in the existing<br />

multi-core cabling to accommodate the requirement for additional signalling from the primary plant. It may be a<br />

requirement to utilise or install auxiliary relays if detailed designs identify that there are insufficient spare cable cores.<br />

The 220 kV bus bar protection scheme will need to accommodate ten substation bays: A4 (transformer T1), B4<br />

(transformer T2), H1 (Sheffield–Farrell No. 1 transmission line), J1 (Sheffield–Farrell 220 kV No. 2 transmission line) ,<br />

D1 (Farrell–Reece No. 1 transmission line), E1 (Farrell–Reece No. 2 transmission line), A1 (Farrell–Tribute<br />

transmission line), B1 (Farrell–John Butters transmission line), (Farrell–Bastyan transmission line), and A7 (bus coupler<br />

bay).<br />

The 110 kV bus bar protection scheme will need to accommodate seven substation bays: A5 (transformer T1), B5<br />

(transformer T2), N1 (Farrell–Que-Savage River–Hampshire transmission line), S1 (Farrell–Rosebery transmission line),<br />

T1 (Farrell–Rosebery–Queenstown transmission line), P1 (Farrell–Mackintosh transmission line) and B7 (bus coupler<br />

bay).<br />

3. INVESTMENT TIMING<br />

The Farrell Substation bus bar protection replacement project has been programmed to commence in early 2009, with<br />

final commissioning in June 2010. The project has been attributed a high priority because of the high likelihood and<br />

impact of critical protection scheme failures.<br />

NPV analysis demonstrates that it is most efficient to start this project in 2009.<br />

The 110 kV bus zone has proven more unreliable than the 220 kV system, so it is proposed to undertake works on this<br />

system first. The project is proposed to be staged as follows:<br />

1. Commission the new 110 kV Bus Zone Protection B scheme (GE Multilin type B90), maintaining the existing<br />

Brown Boveri type INX2 scheme in service. Use the existing spare protection CT of bays for new bus bar<br />

protection scheme<br />

© <strong>Transend</strong> Networks Pty Ltd 3 of 10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!