CONTENTS<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
CONTENTS 2<br />
1 BACKGROUND 3<br />
2 PROJECT OVERVIEW 3<br />
3 PROJECT TIMING 4<br />
4 INVESTMENT NEED 4<br />
4.1 SUMMARY.......................................................................................................................................................... 4<br />
4.2 CIRCUIT BREAKERS ........................................................................................................................................... 5<br />
4.3 DISCONNECTORS................................................................................................................................................ 5<br />
4.4 VOLTAGE TRANSFORMERS................................................................................................................................. 6<br />
4.5 CURRENT TRANSFORMERS ................................................................................................................................. 7<br />
4.6 POWER CABLES.................................................................................................................................................. 7<br />
4.7 POST INSULATORS.............................................................................................................................................. 7<br />
4.8 BUS CONDUCTOR AND FITTINGS......................................................................................................................... 8<br />
4.9 PROTECTION AND CONTROL SYSTEMS................................................................................................................ 8<br />
4.10 NETWORK DEVELOPMENT CONSIDERATIONS ..................................................................................................... 9<br />
5 CUSTOMER CONSULTATION 9<br />
6 BENEFITS 10<br />
7 OPTIONS ANALYSIS 10<br />
7.1 OPTION 1 - MANAGE EXISTING ASSETS AND DEFER REPLACEMENT.................................................................. 10<br />
7.2 OPTION 2 - REPLACE ASSETS IN SITU ................................................................................................................ 11<br />
7.3 OPTION 3 - STAGED REPLACEMENT OF SELECTED ASSETS IN-SITU................................................................... 12<br />
7.4 OPTION 4 - REDEVELOP USING AIR INSULATED SWITCHGEAR ........................................................................... 13<br />
7.5 OPTION 5 - REDEVELOP USING GAS INSULATED SWITCHGEAR .......................................................................... 15<br />
7.6 OPTION 6 - REDEVELOP USING HYBRID SWITCHGEAR ....................................................................................... 16<br />
8 OPTION ESTIMATES 17<br />
9 PREFERRED OPTION 17<br />
© <strong>Transend</strong> Networks Pty Ltd 2 of 17