Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
1 BACKGROUND<br />
Burnie-Waratah 110 kV Transmission Line Wood Poles<br />
TNM-CR-808-0888<br />
Issue 1.0, November 2008<br />
This document assesses the condition of <strong>Transend</strong>’s population of wood poles currently installed<br />
on the Burnie–Waratah 110 kV transmission line.<br />
The Burnie–Waratah 110 kV transmission line was commissioned in 1967 and was constructed as a<br />
single circuit ‘H’ pole line using two treated hardwood poles and a steel crossarm. The<br />
transmission line currently has 422 wood poles and 14 steel poles installed at 223 locations. The<br />
wood poles have installation dates ranging from 1966 to 2001. It is intended that this transmission<br />
line will remain a part of <strong>Transend</strong>’s transmission network in its current form for the foreseeable<br />
future.<br />
The average age of the wood poles on this transmission line is 31 years, with 58 per cent of the<br />
total structures now 42 years old. The wood pole age profile for this transmission line is presented<br />
in figure 1.<br />
The low number of pole replacements between 1981 and 1984 reflect the preference for pole<br />
staking at that time.<br />
Figure 1 – Wood pole age profile as at September 2008<br />
Quantity<br />
300<br />
250<br />
200<br />
150<br />
100<br />
50<br />
0<br />
1966 1975 1981 1982 1983 1984 1991 1993 1994 1995 1996 1997 2001<br />
2 ASSET ASSESSMENT<br />
© <strong>Transend</strong> Networks Pty Ltd Page 5 of 9<br />
Year<br />
Quantity<br />
The assessment of the wood poles is based on the Aurora Energy Pole Inspection and Maintenance<br />
Procedure NP R AM 27-1 which details the standard method for inspection and maintenance<br />
treatment of wood poles.<br />
The wood poles are tested every three years, with the next test due during summer in 2010-11. The<br />
tests are undertaken by Aurora utilising its own proven methodology. Inspectors are responsible for<br />
inspection of poles, pole top hardware and conductors for serviceability and defects, testing and<br />
treatment of poles against wood decay, and recording the details. On completion of the tests,<br />
Aurora provides a report to <strong>Transend</strong> on the condition of each pole on the transmission line.<br />
UNCONTROLLED WHEN PRINTED