24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

1 BACKGROUND<br />

Burnie-Waratah 110 kV Transmission Line Wood Poles<br />

TNM-CR-808-0888<br />

Issue 1.0, November 2008<br />

This document assesses the condition of <strong>Transend</strong>’s population of wood poles currently installed<br />

on the Burnie–Waratah 110 kV transmission line.<br />

The Burnie–Waratah 110 kV transmission line was commissioned in 1967 and was constructed as a<br />

single circuit ‘H’ pole line using two treated hardwood poles and a steel crossarm. The<br />

transmission line currently has 422 wood poles and 14 steel poles installed at 223 locations. The<br />

wood poles have installation dates ranging from 1966 to 2001. It is intended that this transmission<br />

line will remain a part of <strong>Transend</strong>’s transmission network in its current form for the foreseeable<br />

future.<br />

The average age of the wood poles on this transmission line is 31 years, with 58 per cent of the<br />

total structures now 42 years old. The wood pole age profile for this transmission line is presented<br />

in figure 1.<br />

The low number of pole replacements between 1981 and 1984 reflect the preference for pole<br />

staking at that time.<br />

Figure 1 – Wood pole age profile as at September 2008<br />

Quantity<br />

300<br />

250<br />

200<br />

150<br />

100<br />

50<br />

0<br />

1966 1975 1981 1982 1983 1984 1991 1993 1994 1995 1996 1997 2001<br />

2 ASSET ASSESSMENT<br />

© <strong>Transend</strong> Networks Pty Ltd Page 5 of 9<br />

Year<br />

Quantity<br />

The assessment of the wood poles is based on the Aurora Energy Pole Inspection and Maintenance<br />

Procedure NP R AM 27-1 which details the standard method for inspection and maintenance<br />

treatment of wood poles.<br />

The wood poles are tested every three years, with the next test due during summer in 2010-11. The<br />

tests are undertaken by Aurora utilising its own proven methodology. Inspectors are responsible for<br />

inspection of poles, pole top hardware and conductors for serviceability and defects, testing and<br />

treatment of poles against wood decay, and recording the details. On completion of the tests,<br />

Aurora provides a report to <strong>Transend</strong> on the condition of each pole on the transmission line.<br />

UNCONTROLLED WHEN PRINTED

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!