24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The drawbacks for this option are that it:<br />

� results in a higher initial <strong>capital</strong> cost than option 1;<br />

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

� results in a higher overall <strong>capital</strong> cost than option 2, primarily due to contractor remobilisation and increased internal<br />

costs;<br />

� does not align with <strong>Transend</strong>’s policy to utilise dead tank circuit breakers when replacing 110 kV live tank current<br />

transformers and circuit breakers for two 110 kV bays;<br />

� reduced efficiencies in project delivery, in particular co-ordination of works associated with the Avoca Substation<br />

transformer T2 installation project and asset replacement works; and<br />

� will need additional transmission circuit outages to undertake the works.<br />

7.3.4 CONCLUSION<br />

This option is technically viable.<br />

7.4 OPTION 4: COMPLETE REDEVELOPMENT OF PALMERSTON SUBSTATION<br />

110 KV<br />

7.4.1 SCOPE<br />

The scope for this option includes:<br />

� in-situ replacement of the existing live tank circuit breakers with dead tank units that have integral current<br />

transformers;<br />

� replacement of 110 kV disconnectors in situ;<br />

� replacement of gantry structures;<br />

� replacement of protection and control schemes; and<br />

� implement revised maintenance practices.<br />

The <strong>capital</strong> cost of this option is $12.49 million ($June 2007).<br />

7.4.2 BENEFITS<br />

The benefits for this option are that it:<br />

� allows <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives;<br />

� addresses safety issues associated with the 110 kV assets identified in Section 4 of this document, in particular the<br />

110 kV voltage transformers and post insulators;<br />

� addresses other performance, reliability and design issues identified in Section 4 of this document;<br />

� improves operational functionality as new 110 kV disconnectors would be motorised and capable of remote<br />

operation; and<br />

� reduces the ongoing maintenance requirements and costs associated with the site.<br />

7.4.3 DRAWBACKS<br />

The drawbacks for this option are that it:<br />

� would need outages of an extended duration for each transmission circuit because it would be required to replace<br />

110 kV disconnectors and other infrastructure; and<br />

� would require a higher <strong>capital</strong> cost than option 2.<br />

© <strong>Transend</strong> Networks Pty Ltd 12 of 13

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!