1.6.5 Protection and control<br />
<strong>Renewal</strong> Capital Expenditure<br />
TNM-GR-809-0929<br />
Issue 1.0, January 2009<br />
The protection and control systems associated with the 110 kV substation redevelopment projects<br />
comprise predominately electromechanical relays, with some static devices, both types of which<br />
need to be replaced because they are susceptible to component degradation and failure, poor<br />
performance, lack of spares and have minimal functionality.<br />
Electromechanical or static devices are obsolete technologies and require frequent maintenance and<br />
repair compared to modern microprocessor protection schemes. <strong>Transend</strong>’s asset management<br />
plans for protection and control systems recommend that:<br />
(a) protection systems that are unreliable and have exceeded their useful life be progressively<br />
replaced; and<br />
(b) where practicable and cost-effective, protection and control system replacements should be<br />
incorporated with primary asset replacement programs.<br />
1.7 CONCLUSION<br />
<strong>Transend</strong>’s revised revenue proposal is based on the following reasonable requirements for the<br />
110 kV substation redevelopment projects associated with replacement of Reyrolle OS10 circuit<br />
breakers:<br />
Table 7 – Revised revenue proposal ($m 2008–09)<br />
Arthurs Lake Substation 110 kV<br />
redevelopment<br />
Burnie Substation 110 kV<br />
redevelopment<br />
Creek Road Substation 110 kV<br />
redevelopment<br />
Knights Road Substation 110 kV<br />
redevelopment<br />
Meadowbank Substation 110 kV<br />
redevelopment<br />
Palmerston Substation 110 kV<br />
redevelopment<br />
Temco Substation 110 kV<br />
redevelopment<br />
Tungatinah Substation 110 kV<br />
redevelopment<br />
2009–10 2010–11 2011–12 2012–13 2013–14 Total<br />
- - 0.2 2.5 1.4 4.1<br />
- - 1.1 4.9 2.2 8.1<br />
- 1.6 2.7 22.2 6.6 33.1<br />
- - - 1.2 5.4 6.6<br />
- - - 0.8 3.8 4.6<br />
- - 1.8 8.1 3.8 13.7<br />
- - - - 0.5 0.5<br />
- - - 3.3 16.2 19.5<br />
Further information for these projects is provided in <strong>Transend</strong>’s investment evaluation summaries<br />
provided as attachments A1 to A7.<br />
1.8 SECTION A – LIST OF ATTACHMENTS<br />
Attachment Description<br />
A1 110 kV substation transmission circuit asset replacement requirements<br />
A2 Arthurs Lake Substation redevelopment - investment evaluation summary<br />
A3 Burnie Substation 110 kV redevelopment - investment evaluation summary<br />
A4 Creek Road Substation 110 kV redevelopment - investment evaluation summary<br />
Page 20 of 28 © <strong>Transend</strong> Networks Pty Ltd<br />
UNCONTROLLED WHEN PRINTED