24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

Structure site require special attention to ensure that electrical clearances are maintained and that the correct transmission<br />

circuits are identified. <strong>Transend</strong> has implemented a number of interim measures, including improved security fencing,<br />

the installation of barriers and additional signage. However, these interim measures are not acceptable for the long term.<br />

The redevelopment of Tungatinah Substation and Tarraleah Switching Station provides the opportunity to costeffectively<br />

remove the transmission gantry structures that comprise the tee structure and over-pass the Boyer Tee<br />

Structure site. The removal of the gantry structures will eliminate the significant safety risks associated with the grossly<br />

substandard electrical clearances at Boyer Tee Structure.<br />

5 CUSTOMER CONSULTATION<br />

Over the past few years extensive consultation has been undertaken with affected customers with respect to the proposed<br />

110 kV redevelopment of Tungatinah Substation.<br />

<strong>Transend</strong> proposes to purchase additional land to allow the preferred substation configuration to be achieved. <strong>Transend</strong><br />

has compulsory acquisition powers, which will be used if there are issues with the preferred option of purchasing land by<br />

agreement. Given the long lead time before work is to commence, <strong>Transend</strong> is confident that all customer and acquisition<br />

issues associated with this project will be resolved, allowing the project to proceed in the timeframe forecast in the<br />

revenue proposal.<br />

6 BENEFITS<br />

The direct benefits of redeveloping Tungatinah Substation and Tarraleah Switching Station include:<br />

� the major safety risks associated with 110 kV assets and the grossly substandard electrical clearances will be<br />

addressed;<br />

� increased reliability and availability of electricity supply by replacing obsolete, unreliable assets that are in poor<br />

condition;<br />

� increased operational flexibility, with a reduced need to reconfigure the 110 kV transmission network;<br />

� direct operational cost savings due to reduced maintenance costs by replacing high maintenance equipment with<br />

new, modern and low maintenance equipment;<br />

� reduced spares inventory; and<br />

� alignment with strategic asset management plans.<br />

7 OPTIONS ANALYSIS<br />

7.1 PRELIMINARY OPTIONS ANALYSIS SUMMARY<br />

An initial review of options to redevelop Tungatinah Substation and Tarraleah Switching Station was undertaken by<br />

Sinclair Knight Merz in 2005 (refer to SKM’s interim report TRIM D05/2848). The options considered include:<br />

1. upgrade the two stations on their existing sites;<br />

2. rationalise both stations at Tungatinah Substation;<br />

3. rationalise both stations on a greenfield site;<br />

4. upgrade Tungatinah Substation on the existing site and replace Tarraleah Switching Station at a greenfield site.<br />

Sub-options recognised the following factors:<br />

� the possibility of cable interconnection between the two existing stations;<br />

� the possible use of GIS to overcome space limitations;<br />

� the possibility of a distribution system back-up to a single 110/22 kV transformer supply of Aurora Energy;<br />

© <strong>Transend</strong> Networks Pty Ltd 12 of 15

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!