Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
Structure site require special attention to ensure that electrical clearances are maintained and that the correct transmission<br />
circuits are identified. <strong>Transend</strong> has implemented a number of interim measures, including improved security fencing,<br />
the installation of barriers and additional signage. However, these interim measures are not acceptable for the long term.<br />
The redevelopment of Tungatinah Substation and Tarraleah Switching Station provides the opportunity to costeffectively<br />
remove the transmission gantry structures that comprise the tee structure and over-pass the Boyer Tee<br />
Structure site. The removal of the gantry structures will eliminate the significant safety risks associated with the grossly<br />
substandard electrical clearances at Boyer Tee Structure.<br />
5 CUSTOMER CONSULTATION<br />
Over the past few years extensive consultation has been undertaken with affected customers with respect to the proposed<br />
110 kV redevelopment of Tungatinah Substation.<br />
<strong>Transend</strong> proposes to purchase additional land to allow the preferred substation configuration to be achieved. <strong>Transend</strong><br />
has compulsory acquisition powers, which will be used if there are issues with the preferred option of purchasing land by<br />
agreement. Given the long lead time before work is to commence, <strong>Transend</strong> is confident that all customer and acquisition<br />
issues associated with this project will be resolved, allowing the project to proceed in the timeframe forecast in the<br />
revenue proposal.<br />
6 BENEFITS<br />
The direct benefits of redeveloping Tungatinah Substation and Tarraleah Switching Station include:<br />
� the major safety risks associated with 110 kV assets and the grossly substandard electrical clearances will be<br />
addressed;<br />
� increased reliability and availability of electricity supply by replacing obsolete, unreliable assets that are in poor<br />
condition;<br />
� increased operational flexibility, with a reduced need to reconfigure the 110 kV transmission network;<br />
� direct operational cost savings due to reduced maintenance costs by replacing high maintenance equipment with<br />
new, modern and low maintenance equipment;<br />
� reduced spares inventory; and<br />
� alignment with strategic asset management plans.<br />
7 OPTIONS ANALYSIS<br />
7.1 PRELIMINARY OPTIONS ANALYSIS SUMMARY<br />
An initial review of options to redevelop Tungatinah Substation and Tarraleah Switching Station was undertaken by<br />
Sinclair Knight Merz in 2005 (refer to SKM’s interim report TRIM D05/2848). The options considered include:<br />
1. upgrade the two stations on their existing sites;<br />
2. rationalise both stations at Tungatinah Substation;<br />
3. rationalise both stations on a greenfield site;<br />
4. upgrade Tungatinah Substation on the existing site and replace Tarraleah Switching Station at a greenfield site.<br />
Sub-options recognised the following factors:<br />
� the possibility of cable interconnection between the two existing stations;<br />
� the possible use of GIS to overcome space limitations;<br />
� the possibility of a distribution system back-up to a single 110/22 kV transformer supply of Aurora Energy;<br />
© <strong>Transend</strong> Networks Pty Ltd 12 of 15