24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

Reference Compliance obligation Substation issue Project objective<br />

NEMMCO<br />

Operating<br />

Procedure<br />

SO_OP6100<br />

S8.1.3.1<br />

‘Unless agreed to the contrary, after sixteen<br />

hours from the unplanned outage of one<br />

protection of a duplicated scheme the power<br />

system equipment must be switched out of<br />

service unless the protection scheme has been<br />

repaired or temporary protection installed.’<br />

5 CUSTOMER CONSULTATION<br />

Maximum allowable period for an<br />

unplanned outage of one protection<br />

of a duplicated scheme is 16 hours.<br />

The existing protection schemes are<br />

unreliable and are likely to fail.<br />

Provision of an upgraded<br />

220 kV transmission line<br />

protection schemes will<br />

minimise risk of any future<br />

unplanned outage being<br />

greater than 16 hours.<br />

<strong>Transend</strong> will liaise with all relevant stakeholders regarding the planned works at Farrell and Sheffield substations. Outages<br />

will be required for each of the transmission lines to implement the works. Some of these outages will constrain generation,<br />

so it is important that planned outages be well coordinated to ensure that the impact of the planned outages is minimised.<br />

6 BENEFITS<br />

Replacement of the 220 kV transmission line protection schemes at Sheffield and Farrell substations will provide the<br />

following benefits:<br />

� the likelihood of unplanned transmission line protection scheme outages will be reduced, thereby improving the<br />

reliability and security of the transmission network;<br />

� the occurrence of events that cause power flows through Farrell Substation to be constrained will be reduced;<br />

� obsolete, unreliable and difficult to maintain protection schemes will be replaced with modern, reliable equipment that<br />

incorporate self supervision functions, thereby reducing ongoing operations and maintenance costs;<br />

� ensure ongoing compliance with the NER;<br />

� additional disturbance recording and distance to fault facilities will be provided, thereby improving power system<br />

analysis and fault response capability;<br />

� allow full compliance with <strong>Transend</strong>’s internal design standard for the protection of EHV transmission lines;<br />

� reduction in the risk of non-operation of the transmission line protection schemes. If faults are not cleared<br />

appropriately then faults can result in damage to primary equipment, system instability issues and forced outages; and<br />

� reduction in the risk of mal-operation of the transmission line protection schemes due to partial failure of the scheme.<br />

Mal-operation of the scheme (ie operation of the scheme when there is no fault present) can result in forced outages<br />

and system instability issues.<br />

7 OPTIONS ANALYSIS<br />

The following viable options have been considered to address the identified investment needs and compliance issues<br />

associated with the Sheffield–Farrell 220 kV transmission line protection schemes:<br />

� maintain the existing transmission line protection schemes and defer replacement; and<br />

� replace transmission line protection schemes.<br />

An alternative option that included replacing the Main A protection scheme (THR relay) and deferring the replacement of the<br />

Main B protection scheme (MPC relay) additional schemes was considered but discounted because this option would not<br />

provide any material benefits since the existing protection schemes would still be susceptible to failure. It would also create a<br />

technological mismatch between the relays protecting a particular transmission line.<br />

The viable options are discussed in further detail in the following sections.<br />

© <strong>Transend</strong> Networks Pty Ltd 6 of 7

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!