Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
Reference Compliance obligation Substation issue Project objective<br />
NEMMCO<br />
Operating<br />
Procedure<br />
SO_OP6100<br />
S8.1.3.1<br />
‘Unless agreed to the contrary, after sixteen<br />
hours from the unplanned outage of one<br />
protection of a duplicated scheme the power<br />
system equipment must be switched out of<br />
service unless the protection scheme has been<br />
repaired or temporary protection installed.’<br />
5 CUSTOMER CONSULTATION<br />
Maximum allowable period for an<br />
unplanned outage of one protection<br />
of a duplicated scheme is 16 hours.<br />
The existing protection schemes are<br />
unreliable and are likely to fail.<br />
Provision of an upgraded<br />
220 kV transmission line<br />
protection schemes will<br />
minimise risk of any future<br />
unplanned outage being<br />
greater than 16 hours.<br />
<strong>Transend</strong> will liaise with all relevant stakeholders regarding the planned works at Farrell and Sheffield substations. Outages<br />
will be required for each of the transmission lines to implement the works. Some of these outages will constrain generation,<br />
so it is important that planned outages be well coordinated to ensure that the impact of the planned outages is minimised.<br />
6 BENEFITS<br />
Replacement of the 220 kV transmission line protection schemes at Sheffield and Farrell substations will provide the<br />
following benefits:<br />
� the likelihood of unplanned transmission line protection scheme outages will be reduced, thereby improving the<br />
reliability and security of the transmission network;<br />
� the occurrence of events that cause power flows through Farrell Substation to be constrained will be reduced;<br />
� obsolete, unreliable and difficult to maintain protection schemes will be replaced with modern, reliable equipment that<br />
incorporate self supervision functions, thereby reducing ongoing operations and maintenance costs;<br />
� ensure ongoing compliance with the NER;<br />
� additional disturbance recording and distance to fault facilities will be provided, thereby improving power system<br />
analysis and fault response capability;<br />
� allow full compliance with <strong>Transend</strong>’s internal design standard for the protection of EHV transmission lines;<br />
� reduction in the risk of non-operation of the transmission line protection schemes. If faults are not cleared<br />
appropriately then faults can result in damage to primary equipment, system instability issues and forced outages; and<br />
� reduction in the risk of mal-operation of the transmission line protection schemes due to partial failure of the scheme.<br />
Mal-operation of the scheme (ie operation of the scheme when there is no fault present) can result in forced outages<br />
and system instability issues.<br />
7 OPTIONS ANALYSIS<br />
The following viable options have been considered to address the identified investment needs and compliance issues<br />
associated with the Sheffield–Farrell 220 kV transmission line protection schemes:<br />
� maintain the existing transmission line protection schemes and defer replacement; and<br />
� replace transmission line protection schemes.<br />
An alternative option that included replacing the Main A protection scheme (THR relay) and deferring the replacement of the<br />
Main B protection scheme (MPC relay) additional schemes was considered but discounted because this option would not<br />
provide any material benefits since the existing protection schemes would still be susceptible to failure. It would also create a<br />
technological mismatch between the relays protecting a particular transmission line.<br />
The viable options are discussed in further detail in the following sections.<br />
© <strong>Transend</strong> Networks Pty Ltd 6 of 7