Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Renewal</strong> Capital Expenditure<br />
TNM-GR-809-0929<br />
Issue 1.0, January 2009<br />
2 SECTION B: FARRELL AND NEW NORFOLK SUBSTATIONS<br />
SECONDARY SYSTEM REPLACEMENTS PROJECTS<br />
2.1 BACKGROUND<br />
In relation to the Farrell and New Norfolk substation secondary systems replacement projects,<br />
Nuttall Consulting considered that <strong>Transend</strong> had not demonstrated that there will be a positive net<br />
benefit in undertaking the projects in their proposed form 6 . Furthermore Nuttall Consulting argued<br />
that there is a reasonable case for the projects to be undertaken in a staged manner; prioritising the<br />
highest risk elements first. Nuttall Consulting commented that the deferment of the later stages by a<br />
number of years may offset the increased <strong>capital</strong> cost of the staged project.<br />
In response to the draft decision, <strong>Transend</strong> accepts Nuttall Consulting’s finding that the economic<br />
analysis that supported the original Farrell and New Norfolk substation secondary system<br />
replacement projects could be improved. <strong>Transend</strong> has therefore undertaken further detailed<br />
analysis, including risk assessments, to examine different staging options. This further analysis<br />
indicates that some secondary system replacement <strong>capital</strong> <strong>expenditure</strong> can be deferred. The overall<br />
extent of this <strong>capital</strong> <strong>expenditure</strong> deferral is less than recommended by Nuttall Consulting.<br />
2.2 REVISED PROPOSAL<br />
The purpose of this section is to provide further information on the Farrell and New Norfolk<br />
substation secondary systems replacement projects. Each project is discussed separately in the<br />
following sections.<br />
2.2.1 Farrell Substation secondary systems replacements project<br />
The Farrell Substation secondary systems replacements project comprises the replacement of the<br />
following protection schemes:<br />
(a) 110 kV and 220 kV bus bar protection schemes;<br />
(b) Sheffield–Farrell Nos. 1 and 2 220 kV transmission lines protection schemes (at Farrell and<br />
Sheffield substations);<br />
(c) Farrell–Rosebery–Queenstown 110 kV transmission line protection scheme;<br />
(d) Farrell–Rosebery 110 kV transmission line protection scheme;<br />
(e) Farrell–Que–Savage River–Hampshire 110 kV transmission line protection scheme; and<br />
(f) transformers T1 and T2 protection schemes.<br />
The replacement of the 110 kV and 220 kV protection schemes is the highest priority components<br />
of the Farrell Substation secondary system replacements project, primarily because of the potential<br />
impact that a bus bar fault would have on the power system with either scheme out of service, the<br />
unacceptably poor performance of the existing schemes and the unavailability of spares to<br />
undertake repairs.<br />
The Sheffield–Farrell 220 kV transmission lines provide the sole 220 kV connection between the<br />
west coast of Tasmania and the remainder of the transmission network. They connect up to<br />
618 MW of generation to the Tasmanian power system and are frequently operated beyond their<br />
firm capacity. The distance protection schemes associated with these transmission lines comprise<br />
static relays that need to be replaced because they present a reliability risk and are obsolete<br />
technology.<br />
6 Ibid, page 65.<br />
Page 22 of 28 © <strong>Transend</strong> Networks Pty Ltd<br />
UNCONTROLLED WHEN PRINTED