24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

7.2.3 DRAWBACKS<br />

The option has the following drawbacks:<br />

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

� high <strong>capital</strong> cost as the total number of assets replaced is higher than alternative, rationalised arrangements;<br />

� it does not address the operational issues associated with the ring bus arrangement identified in Section 4;<br />

� presents increased risks during implementation working within a constrained, energised site;<br />

� obtaining the required outages to undertake the works will be difficult (in order to allow key equipment to be<br />

decommissioned, civil works including concrete curing, and finally erection and commissioning of the new<br />

equipment);<br />

� long outages will reduce reliability of supply to customers supplied from Creek Road Substation;<br />

� additional temporary works required during implementation to maintain secure and reliable supply at Creek Road<br />

Substation and remote sites; and<br />

� may have implications on future development at the site.<br />

7.2.4 CONCLUSION<br />

This is not the preferred option because it does not address the reliability and performance issues associated with the<br />

110 kV ring bus arrangement at Creek Road Substation. In addition, implementation would be difficult in terms of<br />

obtaining the necessary outages to undertake the works.<br />

7.3 OPTION 3 - STAGED REPLACEMENT OF SELECTED ASSETS IN-SITU<br />

7.3.1 SCOPE<br />

The scope for this option is essentially the same as option 2, but implemented using a staged approach based on<br />

transmission circuit criticality. This option includes:<br />

� initial replacement of assets that have an assigned transmission circuit criticality rating of four or five (13 bays);<br />

� initial replacement of other remaining assets that are known to present a safety risk, including voltage transformers,<br />

current transformers and post insulators in 2014;<br />

� replacement of the underground 110 kV power cable that is in poor condition in 2014; and<br />

� deferred replacement of the remaining 110 kV assets by up to three years (three bays).<br />

The <strong>capital</strong> cost of this option includes an initial $23.20 million ($June 2007) to replace critical assets and to address<br />

safety issues followed by a deferred <strong>capital</strong> cost of $4.22 million ($June 2007) to replace remaining 110 kV assets three<br />

years later.<br />

7.3.2 BENEFITS<br />

The benefits for this option are that it:<br />

� allows <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives in the mid-term;<br />

� addresses the safety issues associated with the 110 kV assets identified in Section 4 of this document;<br />

� defers <strong>capital</strong> <strong>expenditure</strong> associated with lower criticality assets for up to three years;<br />

� addresses the performance issues identified in Section 4 of this document, with the exception of those transmission<br />

circuits that have a criticality less than four; and<br />

� reduces the ongoing maintenance requirements and costs associated with the site.<br />

© <strong>Transend</strong> Networks Pty Ltd 12 of 17

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!