Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
7.2.3 DRAWBACKS<br />
The option has the following drawbacks:<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
� high <strong>capital</strong> cost as the total number of assets replaced is higher than alternative, rationalised arrangements;<br />
� it does not address the operational issues associated with the ring bus arrangement identified in Section 4;<br />
� presents increased risks during implementation working within a constrained, energised site;<br />
� obtaining the required outages to undertake the works will be difficult (in order to allow key equipment to be<br />
decommissioned, civil works including concrete curing, and finally erection and commissioning of the new<br />
equipment);<br />
� long outages will reduce reliability of supply to customers supplied from Creek Road Substation;<br />
� additional temporary works required during implementation to maintain secure and reliable supply at Creek Road<br />
Substation and remote sites; and<br />
� may have implications on future development at the site.<br />
7.2.4 CONCLUSION<br />
This is not the preferred option because it does not address the reliability and performance issues associated with the<br />
110 kV ring bus arrangement at Creek Road Substation. In addition, implementation would be difficult in terms of<br />
obtaining the necessary outages to undertake the works.<br />
7.3 OPTION 3 - STAGED REPLACEMENT OF SELECTED ASSETS IN-SITU<br />
7.3.1 SCOPE<br />
The scope for this option is essentially the same as option 2, but implemented using a staged approach based on<br />
transmission circuit criticality. This option includes:<br />
� initial replacement of assets that have an assigned transmission circuit criticality rating of four or five (13 bays);<br />
� initial replacement of other remaining assets that are known to present a safety risk, including voltage transformers,<br />
current transformers and post insulators in 2014;<br />
� replacement of the underground 110 kV power cable that is in poor condition in 2014; and<br />
� deferred replacement of the remaining 110 kV assets by up to three years (three bays).<br />
The <strong>capital</strong> cost of this option includes an initial $23.20 million ($June 2007) to replace critical assets and to address<br />
safety issues followed by a deferred <strong>capital</strong> cost of $4.22 million ($June 2007) to replace remaining 110 kV assets three<br />
years later.<br />
7.3.2 BENEFITS<br />
The benefits for this option are that it:<br />
� allows <strong>Transend</strong> to achieve the <strong>capital</strong> <strong>expenditure</strong> objectives in the mid-term;<br />
� addresses the safety issues associated with the 110 kV assets identified in Section 4 of this document;<br />
� defers <strong>capital</strong> <strong>expenditure</strong> associated with lower criticality assets for up to three years;<br />
� addresses the performance issues identified in Section 4 of this document, with the exception of those transmission<br />
circuits that have a criticality less than four; and<br />
� reduces the ongoing maintenance requirements and costs associated with the site.<br />
© <strong>Transend</strong> Networks Pty Ltd 12 of 17