24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Burnie-Waratah 110 kV Transmission Line Wood Poles<br />

TNM-CR-808-0888<br />

Issue 1.0, November 2008<br />

EXECUTIVE SUMMARY<br />

This document assesses the condition of <strong>Transend</strong>’s population of wood poles currently installed on the<br />

Burnie–Waratah 110 kV transmission line.<br />

The Burnie–Waratah 110 kV transmission line was commissioned in 1967 and was constructed as a<br />

single circuit ‘H’ pole line with each support structure comprising two treated hardwood poles and a steel<br />

crossarm. The transmission line currently has 422 treated wood poles (two per structure) and 14 steel<br />

poles (one per structure) installed at 223 locations. The wood poles have installation dates ranging from<br />

1966 to 2001.<br />

The wood poles are tested every three years, with the next test regime to commence during summer in<br />

2010-11. These tests are undertaken by contractor Aurora Energy Pty Ltd (Aurora). Aurora is considered<br />

by <strong>Transend</strong> as the treated wood pole experts in Tasmania; in that it successfully manages a population of<br />

over 250 000 wood poles. <strong>Transend</strong> consequently utilise Aurora’s proven pole testing methodology.<br />

The treated wood pole failure rate for this transmission line when compared against the HEC/Aurora<br />

historical and estimated treated wood pole failure rate shows that the wood poles on this transmission line<br />

are failing at a faster rate (Trim Ref D08/68430). The earliest installed treated wood poles on this line are<br />

now 42 years old, and the estimated failure curve indicates that the last original treated wood pole on this<br />

transmission line will be replaced in 2033 (67 years old) as against 2039 (73 years old) from the<br />

HEC/Aurora data. The actual failure curve when forward estimated indicates that at least thirty poles,<br />

installed in 1966, are expected to require replacing in each future three yearly inspection cycle.<br />

During the 1980s the wood poles were reinforced by attaching a separate shorter pole to the existing pole<br />

as a support. This approach was found to be ineffective in providing sufficient support when it was<br />

identified that the internal weakening of the original pole was not only at or below ground level but also<br />

extended well into the upper portion of the pole. The internal weakening was also not limited to rot, but<br />

included a fungal attack through cracks of the outer surface of the pole as it weathers and ages. As such,<br />

reinforcement of an existing weakened pole, either by a separate supporting pole or metal stakes at<br />

ground level, is no longer recognised as a technically viable life extension option. Since the 1980s and<br />

until 2006, all condemned poles and the existing reinforced poles have been replaced with new treated<br />

wood poles.<br />

In 2006, an evaluation was conducted into replacing the wood poles with steel poles, as and when they<br />

were condemned. The report considered replacing both wood poles in the structure with steel poles. The<br />

report found that there was a whole of life premium of 14 per cent in replacing two treated wood poles<br />

with two modern steel poles. Further analysis has identified that replacing two wood poles with a single<br />

steel pole (for suspension structures) and two steel poles (for strain structures) is approximately 16 per<br />

cent cheaper than the traditional method. This revised pole replacement methodology was adopted and is<br />

currently being utilised.<br />

The future management strategy is to progressively replace the wood poles on this transmission line with<br />

steel poles, one at a suspension structure and two at a strain structure, as and when the wood poles are<br />

confirmed condemned through testing.<br />

Historical inspection and test results indicate that approximately 70 structures will be condemned and<br />

require replacement in the next planning period at a total cost of approximately $4.6m dollars.<br />

Page 4 of 9 © <strong>Transend</strong> Networks Pty Ltd<br />

UNCONTROLLED WHEN PRINTED

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!