Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
4 INVESTMENT NEED<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
This project is required to achieve the following <strong>capital</strong> <strong>expenditure</strong> objectives identified in clause 6A.6.7(a) of the<br />
National Electricity Rules (Rules):<br />
� comply with all applicable regulatory obligations associated with the provision of prescribed transmission services;<br />
� maintain the quality, reliability and security of supply of prescribed transmission services; and<br />
� maintain the reliability, safety and security of the transmission system through the supply of prescribed transmission<br />
services.<br />
The key investment drivers for this project are to address identified safety, condition, and performance issues presented<br />
by the primary and secondary assets at Palmerston Substation 110 kV.<br />
4.1 CIRCUIT BREAKERS<br />
The 110 kV circuit breakers (11 units) installed at Palmerston Substation are Reyrolle type 110/OS/10 units. The<br />
Reyrolle Type 110/OS/10 110 kV Circuit Breaker Condition Assessment Report (TNM-CR-806-0772) recommends that<br />
the units at Palmerston Substation be replaced. The circuit breaker condition assessment has been based on key asset<br />
management considerations including technical, design, reliability, condition, maintenance, spares and contingency<br />
planning, life-cycle and environmental issues. The condition assessment report provides details of the many failures and<br />
defects associated with Reyrolle 110 kV circuit breakers, including those installed at Palmerston Substation. The<br />
condition assessment report has identified the Reyrolle type 110/OS/10 circuit breakers:<br />
� have a number of inherent technical and design deficiencies that have adversely impacted transmission circuit<br />
reliability and availability;<br />
� are unreliable, in particular the air and insulating oil systems;<br />
� are maintenance intensive and costly to maintain when compared with modern equivalent units;<br />
� require spare parts that are no longer available from the manufacturer’s agent;<br />
� require skilled personnel to maintain - the availability of specialised maintenance resources is declining; and<br />
� have reached the end of their useful service lives.<br />
All other transmission companies in Australia and New Zealand have already replaced their population of Reyrolle type<br />
110/OS/10 circuit breaker, or are in the process of doing so, for the same reasons outlined above. <strong>Transend</strong>’s reasons for<br />
replacing this type of circuit breaker are no different to those of other industry participants.<br />
The average preventive maintenance costs associated with the 110 kV circuit breakers at Palmerston Substation include:<br />
� circuit breaker maintenance: $8,300 per circuit breaker (six yearly);<br />
� insulating oil costs: $4,200 per circuit breaker (six yearly);<br />
� compressor maintenance: $1,000 per compressor (six-monthly for the two compressors at Palmerston Substation);<br />
� silica gel maintenance: $500 per circuit breaker (two yearly); and<br />
� pressure inspection costs: $300 per circuit breaker (three yearly).<br />
In addition, the average historic repair cost for a failure or defect associated with a Reyrolle type 110/OS/10 circuit<br />
breaker is $4,730.<br />
Further information on the circuit breaker population can also be found in the Extra High Voltage Circuit Breaker Asset<br />
Management Plan (TNM-PL-809-0541).<br />
© <strong>Transend</strong> Networks Pty Ltd 5 of 13