Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
secondary assets as defined by Sinclair Knight Merz in its ‘Assessment of Economic Lives for <strong>Transend</strong> Regulatory<br />
Asset Classes’ report prepared in April 2008 provided as attachment 24 of <strong>Transend</strong>’s revenue proposal. A large<br />
proportion of the primary assets at Tungatinah Substation and Tarraleah Switching Station will be at least 63 years old<br />
when decommissioned.<br />
Figure 3 – Summary of age and value ($000) of major 110 kV assets installed at Tungatinah Substation<br />
and Tarraleah Switching Station<br />
3 INVESTMENT TIMING<br />
The project is currently scheduled to commence in 2012 and be completed in 2015.<br />
The independent review undertaken by Ascension Consulting recommended that the Tungatinah Substation 110 kV<br />
redevelopment project be implemented as soon as practicable. This project has been scheduled to commence as soon as<br />
practicable, however it has been deferred primarily because of the need to determine the optimum transmission network<br />
configuration. This project has required considerable customer consultation and can only commence once the final stage<br />
of the Southern Power System Security program (the Waddamana–Lindisfarne 220 kV transmission line project) is<br />
completed.<br />
The Tungatinah Substation 110 kV redevelopment project has been coordinated with the Meadowbank Substation<br />
110 kV redevelopment and New Norfolk Substation 110 kV protection replacements projects to enable new, current<br />
differential protection schemes to be installed on the connecting transmission lines, thereby improving the security and<br />
reliability of the transmission network in southern Tasmania.<br />
The revised timing of the project has also been co-ordinated with the Creek Road Substation 110 kV redevelopment<br />
project given the likely synergies in project implementation methodologies.<br />
The Tungatinah Substation 110 kV redevelopment project is currently the third highest ranking of all proposed projects<br />
and the second highest renewal project (ranked closely behind the Creek Road 110 kV redevelopment project) in<br />
<strong>Transend</strong>’s works prioritisation tool, primarily because of the safety issues presented by the assets at Tungatinah<br />
Substation and Tarraleah Switching Station and the criticality of these sites.<br />
It is possible that some works may need to be implemented prior to the planned commencement of the project because of<br />
the deteriorated condition of certain assets and the fact that additional asset condition issues will most likely be identified<br />
prior to commencement of the project.<br />
4 INVESTMENT NEED<br />
This project is required to achieve the following <strong>capital</strong> <strong>expenditure</strong> objectives identified in clause 6A.6.7(a) of the<br />
National Electricity Rules (Rules):<br />
© <strong>Transend</strong> Networks Pty Ltd 5 of 15