Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
Figure 1 – Summary of age and value ($000) of major 110 kV assets installed at Creek Road Substation<br />
3 PROJECT TIMING<br />
The Creek Road Substation 110 kV redevelopment project was originally scheduled to be completed in 2008–09. The<br />
project has been deferred because of the need to coordinate the project with the Hobart Area Supply Upgrade program<br />
and the Southern Power System Security program. These programs have been attributed a higher priority because of the<br />
immediate need to increase the capacity of the transmission and distribution systems in southern Tasmania.<br />
Progressing the Creek Road Substation redevelopment project as per the original schedule would have increased the risk<br />
of supply to Hobart’s CBD if undertaken in parallel with the above-mentioned programs of work. It would also have<br />
been inefficient due to sequencing implications and re-work required. Interim risk mitigation measures have been put in<br />
place to enable this project to be deferred until the final stage of the Southern Power System Security program (the<br />
Waddamana–Lindisfarne 220 kV transmission line project) is completed. The Hobart Area Supply Upgrade program has<br />
been completed in the current regulatory control period. The Creek Road Substation 110 kV redevelopment project is<br />
scheduled to commence in 2012 and be completed in 2014.<br />
The Creek Road Substation 110 kV redevelopment project is currently the highest ranking of all proposed projects in<br />
<strong>Transend</strong>’s works prioritisation tool, primarily because of its importance within the transmission network and the<br />
criticality of the load connected to the substation.<br />
It is possible that further works may need to be implemented prior to the planned commencement of the project because<br />
of the deteriorated condition of certain assets and the fact that additional asset condition issues will most likely be<br />
identified prior to commencement of the project.<br />
4 INVESTMENT NEED<br />
4.1 SUMMARY<br />
This project is required to achieve the following <strong>capital</strong> <strong>expenditure</strong> objectives identified in clause 6A.6.7(a) of the<br />
National Electricity Rules (Rules):<br />
� comply with all applicable regulatory obligations associated with the provision of prescribed transmission services;<br />
� maintain the quality, reliability and security of supply of prescribed transmission services; and<br />
� maintain the reliability, safety and security of the transmission system through the supply of prescribed transmission<br />
services.<br />
© <strong>Transend</strong> Networks Pty Ltd 4 of 17