24.02.2013 Views

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

Transend - Appendix 5 Renewal capital expenditure - Australian ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

5. CUSTOMER CONSULTATION<br />

0BInvestment Evaluation Summary<br />

TNM-GS-809-0720<br />

<strong>Transend</strong> has liaised with all relevant stakeholders regarding the planned works at Farrell Substation. Short outages will<br />

be required for each of the transmission line, transformer, and bus coupler circuits to implement the works. Some of<br />

these outages will constrain generation, so it is important that planned outages be coordinated with Hydro Tasmania to<br />

ensure that the impact of the planned outages is minimised.<br />

6. BENEFITS<br />

Replacement of the 220 kV and 110 kV bus bar protection schemes at Farrell Substation will provide the following<br />

benefits:<br />

� the likelihood of unplanned bus bar protection scheme outages will be reduced, thereby improving the reliability<br />

and security of the transmission network;<br />

� the occurrence of events that cause power flows through the substation to be constrained will be reduced;<br />

� obsolete, unreliable and difficult to maintain protection schemes will be replaced with modern, reliable<br />

equipment that incorporate self supervision functions, thereby reducing ongoing operations and maintenance<br />

costs; and<br />

� ensure ongoing compliance with the NER;<br />

� facilitate future <strong>capital</strong> works at Farrell Substation;<br />

� additional disturbance recording facilities will be provided, thereby improving power system analysis and fault<br />

response capability.<br />

� reduction in the risk of non-operation of the bus bar protection scheme for bus bar faults. If faults are not<br />

cleared appropriately then bus bar faults can result in damage to primary equipment, system instability issues<br />

and forced outages; and<br />

� reduction in the risk of mal-operation of the bus bar protection schemes due to partial failure of the scheme.<br />

Mal-operation of the scheme (ie operation of the scheme when there is no fault present) can result in forced<br />

outages and instability issues.<br />

7. OPTIONS ANALYSIS<br />

The following viable options have been considered to address the identified investment needs and compliance issues<br />

associated with the bus bar protection schemes at Farrell Substation:<br />

1. maintain the existing bus bar protection schemes and defer replacement;<br />

2. replace the 110 kV and 220 kV bus bar protection schemes at Farrell Substation without installing duplicate<br />

systems; and<br />

3. replace the 110 kV and 220 kV bus bar protection schemes at Farrell Substation and install duplicate systems.<br />

An alternative option that included maintaining the existing bus bar protection schemes and installing additional schemes<br />

was considered but discounted because it did not provide any material benefits. The existing bus bar protection schemes<br />

would still be susceptible to failure and would not be able to be repaired because spare components are not available.<br />

The viable options are discussed in further detail in the following sections.<br />

7.1- MAINTAIN THE EXISTING BUS BAR PROTECTION SCHEMES AND DEFER<br />

REPLACEMENTS<br />

This option comprises maintaining the existing Brown Boveri type INX2 bus bar protection schemes.<br />

© <strong>Transend</strong> Networks Pty Ltd 8 of 10

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!