<strong>Renewal</strong> Capital Expenditure<br />

TNM-GR-809-0929<br />

Issue 1.0, January 2009<br />

The planned transmission line distance protection scheme replacements at Chapel Street, Creek<br />

Road and Meadowbank substations and Tarraleah Switching Station provide an opportunity to<br />

cost-effectively replace the transmission line distance protection schemes at New Norfolk<br />

Substation. The replacement schemes will comprise duplicated current differential schemes that<br />

will improve protection co-ordination and improve the performance of the transmission network.<br />

<strong>Transend</strong>’s experience is that if the replacement of protection schemes at either end of the<br />

transmission line is undertaken years apart, there is a significant likelihood that compatible current<br />

differential relays will not be available. Given the fast rate of change in relay technology, it is<br />

prudent to replace protection schemes at both ends of a transmission line at the same time.<br />

2.3 CONCLUSION<br />

<strong>Transend</strong>’s revised revenue proposal is based on the following reasonable requirements for the<br />

Farrell and New Norfolk substations secondary replacement projects:<br />

Table 8 – Revised revenue proposal ($m 2008–09)<br />

Farrell Substation secondary<br />

systems replacements<br />

New Norfolk Substation 110 kV<br />

protection replacements<br />

2009–10 2010–11 2011–12 2012–13 2013–14 Total<br />

2.0 6.8 - - - 8.8<br />

- - 0.1 1.3 4.4 5.8<br />

Further information for these projects is provided in <strong>Transend</strong>’s investment evaluation summaries<br />

provided as attachments B1 to B3.<br />

2.4 SECTION B - LIST OF ATTACHMENTS<br />

Attachment Description<br />

B1 Farrell Substation 110 kV and 220 kV bus bar protection scheme replacements -<br />

investment evaluation summary<br />

B2 Sheffield–Farrell 220 kV transmission lines protection schemes replacements -<br />

investment evaluation summary<br />

B3 New Norfolk Substation 110 kV protection replacements - investment evaluation<br />

summary<br />

Page 24 of 28 © <strong>Transend</strong> Networks Pty Ltd<br />