Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
Transend - Appendix 5 Renewal capital expenditure - Australian ...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
4.1 CIRCUIT BREAKERS<br />
0BInvestment Evaluation Summary<br />
TNM-GS-809-0720<br />
The 110 kV circuit breakers (three units) installed at Meadowbank Substation are Reyrolle type 110/OS/10 units. The<br />
Reyrolle Type 110/OS/10 110 kV Circuit Breaker Condition Assessment Report (TNM-CR-806-0772) assesses the<br />
condition of Reyrolle type 110/OS/10 circuit breakers and recommends that the units at Meadowbank Substation be<br />
replaced. The circuit breaker assessment has been based on key asset management considerations, including technical,<br />
design, reliability, condition, maintenance, spares and contingency planning, life-cycle and environment issues. The<br />
condition assessment report provides details of the many failures and defects associated with Reyrolle 110 kV circuit<br />
breakers, including those installed at Meadowbank Substation. The condition assessment report has identified that the<br />
Reyrolle type 110/OS/10 circuit breakers:<br />
� have a number of inherent technical and design deficiencies that have adversely impacted transmission circuit<br />
reliability and availability;<br />
� are unreliable, in particular the air and insulating oil systems;<br />
� are maintenance intensive and costly to maintain when compared with modern equivalent units;<br />
� require spare parts that are no longer available from the manufacturer’s agent;<br />
� require skilled personnel to maintain - the availability of specialised maintenance resources is declining; and<br />
� have reached the end of their useful service lives.<br />
All other transmission companies in Australia and New Zealand have already replaced their population of Reyrolle type<br />
110/OS/10 circuit breakers, or are in the process of doing so, for the same reasons outlined above. <strong>Transend</strong>’s reasons for<br />
replacing this type of circuit breaker are no different to those of other industry participants.<br />
The 110 kV circuit breakers at Meadowbank Substation will be 52 years old when decommissioned, and will have<br />
exceeded their assigned class life of 45 years as defined by Sinclair Knight Merz in its Assessment of Economic Lives<br />
for <strong>Transend</strong> Regulatory Classes, April 2008.<br />
The preventive maintenance costs associated with the 110 kV circuit breakers at Meadowbank Substation include:<br />
� circuit breaker maintenance: $8 300 per circuit breaker (six yearly);<br />
� insulating oil costs: $4 200 per circuit breaker (six yearly);<br />
� compressor maintenance: $1 000 per compressor (six-monthly for the compressor at Meadowbank Substation);<br />
� silica gel maintenance: $500 per circuit breaker (two yearly); and<br />
� pressure inspection costs: $300 per circuit breaker (three yearly).<br />
� In addition, the average historic repair cost for a failure or defect associated with a Reyrolle type 110/OS/10 circuit<br />
breaker is $4 730.<br />
Further information on the circuit breaker population can also be found in the Extra High Voltage Circuit Breaker Asset<br />
Management Plan (TNM-PL-809-0541).<br />
4.2 VOLTAGE TRANSFORMERS<br />
The 110 kV voltage transformers installed at Meadowbank Substation comprise the following types:<br />
� Balteau type UEV110 - 3 units (average age of 30 years); and<br />
� Ducon type PD - 2 units (45 years).<br />
Balteau voltage transformers<br />
The Balteau type UEV110 voltage transformers have a number of design deficiencies, including:<br />
� the design is susceptible to moisture ingress. Instances of moisture ingress through the diaphragm have occurred,<br />
which has resulted in the high percentage power factor readings of other Balteau units installed in the transmission<br />
network;<br />
� a poorly designed oil-level sight glass. The sight glass is susceptible to mechanical failure and vandalism. The<br />
failure of a sight glass will allow moisture to enter the expansion chamber and pool on the rubber diaphragm. It is<br />
extremely difficult to assess the integrity of the sight glass with the voltage transformer in service; and<br />
� units do not have oil-sampling facilities.<br />
© <strong>Transend</strong> Networks Pty Ltd 5 of 12